History
  • No items yet
midpage
Precision Pipeline, LLC v. Trico Surveying & Mapping, Inc.
712 F. App'x 144
| 3rd Cir. | 2017
Read the full case

Background

  • Dominion hired Trico to survey/map a pipeline route and G-A-I for environmental consulting; Trico’s drawings were provided to bidders, including Precision.
  • Trico’s contract required identification of above-ground foreign crossings and underground crossings only if marked above ground; G-A-I was not required to add crossing info.
  • Precision won the bid but warned in its bid letter that unknown pipelines might exist and proposed negotiating crossing pricing if selected; no such negotiation occurred.
  • During construction Precision encountered 357 foreign crossings though Trico’s drawings showed 89, increasing Precision’s costs substantially.
  • Precision sued Trico and G-A-I for negligent misrepresentation under Restatement (Second) of Torts § 552 as adopted in Bilt‑Rite; District Court granted summary judgment for defendants and this appeal followed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether defendants owed Precision a duty under Bilt‑Rite/§552 to identify ~85% of foreign crossings Trico/G‑A‑I knew drawings would be relied on by bidders/contractors and thus owed a duty to identify industry‑standard percentage of crossings No contract privity with Precision; defendants’ contractual duties to owner did not impose broader duties to third‑party contractors to identify unrequired features Court: No duty owed — Bilt‑Rite liability is limited and arises from breach of duties the professional owed the owner; cannot be expanded to impose open‑ended duties to unknown third parties
Whether district court erred by using common‑law duty factors when applying Bilt‑Rite Bilt‑Rite alone controls; district court improperly supplanted it with broader common‑law duty analysis Following Bilt‑Rite, courts may examine common‑law duty factors to define §552’s scope; such analysis is proper Court: District Court properly considered common‑law duty factors in deciding whether to extend Bilt‑Rite
Whether claim was time‑barred (statute of limitations) District court incorrectly applied limitations bar District court correctly found suit untimely Court: Did not reach merits because no duty; even if Precision were correct on limitations, affirmance would stand
Whether Precision justifiably relied on Trico’s drawings Precision reasonably relied on drawings for bidding decisions No reasonable jury could find justifiable reliance given limits in drawings and Precision’s bid warning Court: Did not resolve reliance issue because lack of duty dispositive

Key Cases Cited

  • Bilt‑Rite Contractors, Inc. v. The Architectural Studio, 866 A.2d 270 (Pa. 2005) (adopting Restatement §552 and limiting negligent‑misrepresentation liability for design professionals to a narrow class of foreseeable third‑party users)
  • S.H. ex rel. Durrell v. Lower Merion Sch. Dist., 729 F.3d 248 (3d Cir. 2013) (statement of summary judgment standard on appeal)
  • Davidson & Jones, Inc. v. County of New Hanover, 255 S.E.2d 580 (N.C. App. 1979) (reasoning adopted by Bilt‑Rite regarding contractor claims against design professionals)
Read the full case

Case Details

Case Name: Precision Pipeline, LLC v. Trico Surveying & Mapping, Inc.
Court Name: Court of Appeals for the Third Circuit
Date Published: Oct 24, 2017
Citation: 712 F. App'x 144
Docket Number: 16-3990
Court Abbreviation: 3rd Cir.