Portage Exteriors v. Hein Constr., Inc.
2014 Ohio 2930
Ohio Ct. App.2014Background
- Portage Exteriors subcontracted with Hein Construction to perform EIFS (synthetic stucco) replacement and caulking on a public school; subcontract price with a change order totaled $109,480.62.
- Portage performed mock-ups per the project Specifications (which required silicone sealant and a 20-year warranty) but used a urethane sealant on the job and delayed joint cleaning/installation.
- A pull test failed; manufacturer refused to issue the 20-year warranty and Hein hired Buckeye to redo the caulking and obtain the warranty. Hein withheld further payments to Portage after an initial payment of $19,800.
- Portage sued Hein for breach of contract and under Ohio's Prompt Pay Act; Hein counterclaimed. At bench trial the court found Portage’s work noncompliant with the Plans/Specifications, awarded Portage $18,350.43 (including a $2,475 prior summary-judgment award), and denied attorney fees based on a finding of a good-faith dispute.
- On appeal the court (this opinion) addressed four assignments of error and reversed and remanded with instructions: include Plans/Specifications in the subcontract interpretation, remove a duplicative $20,000 warranty charge (increasing Portage’s award to $38,350.43), remand for an attorney-fee hearing on the Prompt Pay Act claim, and include statutorily required interest on the Prompt Pay portion.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether subcontract incorporates separate Plans and Specifications | Subcontract (one-page PO + change order) is the full, final agreement; Specs not incorporated | Hein: parties reviewed and intended compliance with Plans/Specs; ambiguous subcontract language references "per plans" and "addendums" | Court: Ambiguous phrases allowed extrinsic evidence; Plans/Specs were incorporated by parties' course of dealings and intent |
| Whether Portage should be charged $20,000 for absence of warranty (and whether that was double-charged) | No competent evidence warranty cost $20,000; court double-counted same cost | Hein: ULSD withheld $20,000 retention due to missing warranty; Hein paid Buckeye to replace work and obtain warranty | Held: Court erred to include $20,000 separately because Buckeye’s replacement (paid $56,996) included the warranty; trial award increased by $20,000 (to $38,350.43) |
| Whether Portage is entitled to attorney fees for Prompt Pay Act recovery of $2,475 | R.C. 4113.61 requires prevailing party fees; trial court never held required hearing | Hein argued good-faith dispute justified denial | Held: Portage entitled to a hearing on fees; remand for attorney-fee determination under the Prompt Pay Act |
| Whether judgment entry omitted required interest/costs and was otherwise deficient | Judgment failed to award post-judgment interest at statutory 18% on Prompt Pay portion and omitted costs; court said it would hold further proceedings on fees but did not | Hein relied on court's good-faith-dispute finding to avoid fees/costs | Held: Court must include statutorily-required 18% interest on the $2,475 Prompt Pay award and address fees/costs on remand; judgment reversed and remanded for entry of corrected judgment and fee hearing |
Key Cases Cited
- Alexander v. Buckeye Pipe Line Co., 53 Ohio St.2d 241 (Ohio 1978) (contract construction is a question of law)
- Aultman Hosp. Assn. v. Community Mut. Ins. Co., 46 Ohio St.3d 51 (Ohio 1989) (when contract terms are clear, court may not look beyond the writing)
- Bellman v. Am. Internatl. Group, 113 Ohio St.3d 323 (Ohio 2007) (parol-evidence rule and final written agreements)
- C.E. Morris Co. v. Foley Constr. Co., 54 Ohio St.2d 279 (Ohio 1978) (bench-trial judgments must be supported by some competent, credible evidence)
- Gerijo, Inc. v. Fairfield, 70 Ohio St.3d 223 (Ohio 1994) (appellate deference to trial court factfindings when evidence allows multiple interpretations)
- Kalain v. Smith, 25 Ohio St.3d 157 (Ohio 1986) (weight and credibility of evidence are for the trier of fact)
- Seasons Coal Co. v. Cleveland, 10 Ohio St.3d 77 (Ohio 1984) (same)
