History
  • No items yet
midpage
Picerne Construction Corp. v. Castellino Villas
199 Cal. Rptr. 3d 257
Cal. Ct. App.
2016
Read the full case

Background

  • Picerne Construction contracted to build an 11‑building apartment complex (Castellino Villas). Construction progressed through mid‑2006; city issued certificates of occupancy between May 3 and July 25, 2006. Owner did not release retained funds.
  • Picerne and subcontractors continued work after July 25, 2006 (notably grip tape on stair treads installed Sept. 15, 18, 19, 2006; roofing work continued into Sept. 2006). Owner signed an "Owner’s Acceptance of Site" on Sept. 8, 2006.
  • Picerne recorded a mechanic’s lien on Nov. 28, 2006 and filed a foreclosure complaint Dec. 29, 2006 (initially naming Doe defendants). The parties arbitrated related claims; arbitration and later proceedings produced awards, settlements, and a Bankruptcy Court plan incorporating a settlement.
  • The trial court (bench) found Picerne’s lien timely, valid, senior to Bank of the West, and fixed a foreclosure judgment (later adjusted by this appeal).
  • Castellino and Bank of the West appealed, raising timeliness of the lien recording, judicial estoppel, whether each building was a separate "residential unit," and errors in lien-amount calculation; Bank of the West also argued Picerne’s suit against it was time‑barred.

Issues

Issue Plaintiff's Argument (Picerne) Defendant's Argument (Castellino / Bank) Held
Timeliness of lien recording under former Civ. Code § 3115 Lien recorded within 90 days after "completion" (owner acceptance on Sept. 8, 2006), so timely Recording period began at substantial completion (e.g., city COs July 25, 2006); lien untimely Court held "completion" means actual completion / owner acceptance; substantial evidence supports Sept. 8, 2006; lien timely recorded
Judicial estoppel (contradictory positions in arbitration v. trial) Picerne may litigate lien timeliness in state court post‑arbitration and bankruptcy settlement Castellino: Picerne argued earlier completion in arbitration to avoid delay liquidated damages, so should be estopped Court rejected application of judicial estoppel; no clear, inconsistent positions requiring estoppel
Whether each apartment building is a separate "residential unit" under § 3131 (multiple filing windows) Single work of improvement; one completion governs Each building is a separate residential unit → separate 90‑day deadlines; many buildings’ liens untimely Court held the project was a single residential unit for § 3131 purposes (no separate titles or separate notices); single filing window applied
Amount of lien and related offsets (principal, setoffs, subcontractor settlements, interest/penalties) Lien should reflect arbitration principal net of prompt payment penalties, setoffs, settlements; include prejudgment interest and prompt payment penalties appropriately Castellino argued trial court overstated principal, failed to subtract setoff, should deduct unpaid subcontractor liens and defense costs, and exclude certain interest/penalties Court adjusted judgment: correct principal = $1,366,338.91; must subtract $115,453.50 setoff and $176,222.10 paid to settling subcontractors; trial court properly included prejudgment interest and 2% prompt‑payment penalties; final modified lien $2,416,855.06
Whether Picerne’s foreclosure suit against Bank of the West was time‑barred under § 3144 for failing to name bank within 90 days Picerne filed foreclosure within 90 days and used Doe defendants, later substituting Bank when it learned of bank’s interest Bank: Picerne knew or should have known bank’s interest and thus needed to name bank within 90 days Court found substantial evidence that Picerne lacked actual knowledge of Bank of the West’s deed of trust; naming as Doe and later substituting satisfied § 3144; suit not time‑barred

Key Cases Cited

  • Moorefield Constr., Inc. v. Intervest–Mortgage Inv. Co., 230 Cal.App.4th 146 (Cal. Ct. App.) (standard of review and statutory interpretation for former § 3115)
  • T.O. IX, LLC v. Superior Court, 165 Cal.App.4th 140 (Cal. Ct. App.) (mechanic’s lien statutory purpose and liberal construction)
  • Connolly Dev., Inc. v. Superior Court of Merced County, 17 Cal.3d 803 (Cal.) (mechanic’s lien principles; lien attaches to owner’s interests)
  • Coast Central Credit Union v. Superior Court, 209 Cal.App.3d 703 (Cal. Ct. App.) (failure to timely record lien precludes enforcement)
  • MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., 36 Cal.4th 412 (Cal.) (doctrine and elements of judicial estoppel)
  • Union Supply Co. v. Morris, 220 Cal. 331 (Cal.) (completion requires contractually required work to be finished; post‑amendment interpretation)
  • Scott, Blake & Wynne v. Summit Ridge Estates, 251 Cal.App.2d 347 (Cal. Ct. App.) (completion = when contractor completed contractual obligations)
  • Hammond Lumber Co. v. Yeager, 185 Cal. 355 (Cal.) (owner acceptance and occupancy support completion finding)
  • Howard S. Wright Constr. Co. v. BBIC Investors, LLC, 136 Cal.App.4th 228 (Cal. Ct. App.) (interpreting "completes his contract" phrase; not dispositive on "completion" issue)
Read the full case

Case Details

Case Name: Picerne Construction Corp. v. Castellino Villas
Court Name: California Court of Appeal
Date Published: Feb 18, 2016
Citation: 199 Cal. Rptr. 3d 257
Docket Number: C071197
Court Abbreviation: Cal. Ct. App.