Petro Star Inc. v. Federal Energy Regulatory Commission
835 F.3d 97
| D.C. Cir. | 2016Background
- The Trans Alaska Pipeline System (TAPS) carries commingled North Slope crude to Valdez; the Quality Bank (administered by FERC) makes zero-sum monetary adjustments to compensate shippers for quality differences among nine distillation "cuts," including Resid (the heaviest).
- Six cuts have published market prices; three (Light Distillate, Heavy Distillate, Resid) are "pre-market" and are valued by deducting hypothetical processing costs from finished-product prices. Resid is valued as coke less processing costs.
- The Quality Bank’s Resid processing-cost deduction includes a 20% capital recovery factor (capital investment allowance) adopted in prior proceedings. Petro Star and Flint Hills challenged that inclusion as undervaluing Resid.
- FERC initiated an investigation (2013), held an ALJ hearing, and the ALJ rejected Petro Star for (1) failing to propose a viable alternative methodology and (2) failing to show the capital allowance was unjust or unreasonable. FERC affirmed; Petro Star sought review.
- The D.C. Circuit found Petro Star submitted new and sufficiently compelling evidence (the "less-than-a-barrel" anomaly and West Coast coking-market data) that warranted a reasoned agency response, but concluded FERC and the ALJ failed to address that evidence adequately.
- The court remanded for FERC to either reconsider Resid’s valuation methodology or provide a reasoned explanation for retaining the capital recovery factor; the State of Alaska lacked standing to intervene on its asserted issue.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether FERC reasonably retained a 20% capital recovery factor in Resid's processing-cost deduction | Petro Star: Short-run market prices for marketable cuts exclude capital recovery; including a 20% allowance undervalues Resid and creates inconsistency with other cut valuations | FERC: No showing of unjustness; record does not compel removing the allowance; Petro Star failed to propose a viable alternative | Court: FERC failed to respond meaningfully to new evidence (anomaly and market data); remand required for reasoned analysis or remedy |
| Whether Petro Star had to propose a fully consistent alternative methodology to obtain relief | Petro Star: Removing capital allowance for Resid would correct a distortion and is appropriately focused on Resid valuation | FERC: Petro Star failed burden because it did not propose a consistent valuation for all pre-market cuts | Court: FERC's rejection on that ground was circular—it assumed the correctness of the contested capital allowance; failure to propose an alternative cannot be an independent basis here |
| Whether the "less-than-a-barrel" anomaly undermines the Quality Bank methodology | Petro Star: From 2009–2012, Quality Bank composite cut values were lower than ANS barrel prices, suggesting Resid undervaluation | FERC/ALJ: Composite comparison is irrelevant because Quality Bank aims only to assign accurate relative values | Court: Because the Quality Bank seeks to mirror market prices under its method, FERC/ALJ failed to explain or rebut the anomaly adequately |
| Whether the State of Alaska may litigate a broader standard for Quality Bank challenges | Alaska: Parties should be allowed to propose superior, pro-competitive methodologies; FERC failed to address that argument | Petro Star (and FERC): Not raised by petitioner; no concrete injury alleged | Court: Alaska lacks Article III standing and may not expand issues beyond the petitioner; claim dismissed |
Key Cases Cited
- OXY USA, Inc. v. FERC, 64 F.3d 679 (D.C. Cir. 1995) (Quality Bank must assign accurate relative values among cuts)
- Tesoro Alaska Petroleum Co. v. FERC, 234 F.3d 1286 (D.C. Cir. 2000) (agency must respond meaningfully to new evidence warranting reexamination)
- Exxon Co., USA v. FERC, 182 F.3d 30 (D.C. Cir. 1999) (deference to agency technical expertise but requires rational explanation)
- Lujan v. Defenders of Wildlife, 504 U.S. 555 (1992) (Article III standing requirements)
- Chenery Corp. v. SEC, 318 U.S. 80 (1943) (agency cannot rely on post hoc rationalizations)
- Tagg Bros. & Moorhead v. United States, 280 U.S. 420 (1930) (new evidence can require modification of rate orders)
- Cities of Bethany v. FERC, 727 F.2d 1131 (D.C. Cir. 1984) (appellate court may affirm on ALJ reasoning when adopted by agency)
- Shell Oil Co. v. FERC, 47 F.3d 1186 (D.C. Cir. 1995) (desire for a different legal rationale absent concrete harm does not confer standing)
- NARUC v. ICC, 41 F.3d 721 (D.C. Cir. 1994) (intervenors cannot expand scope beyond principal parties)
- California Dep’t of Water Res. v. FERC, 306 F.3d 1121 (D.C. Cir. 2002) (limitations on issues intervenors may raise)
