History
  • No items yet
midpage
254 P.3d 1246
Idaho
2011
Read the full case

Background

  • PCM and the Bells entered a cost-plus contract to build a log home; Bells were to pay invoices within ten days and object in writing within five days of invoicing.
  • Neubert, PCM supervisor, billed at $60/hour during supervisory periods but actual wage was $25/hour; Bells were charged $37.39/hour when non-supervisory.
  • Bells initially paid some invoices but disputed portions and terminated PCM before completion; PCM recorded a lien for $113,312.94.
  • District court held an expedited lien hearing, excluding architect and plumber testimony on construction defects, limiting evidence to lien amount reasonableness.
  • Court found PCM prevailed on the lien and awarded damages, then granted summary judgment dismissing Bells’ counterclaims for lack of timely NORA notice.
  • On appeal, Bells challenged evidentiary ruling, lien amount, attorney fees, and the NORA summary judgment; the supreme court vacated the ruling on evidence and remanded.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the district court err in excluding defect-related testimony? Bells relied on defects to defense lien amount. Evidence relates to counterclaims, not lien; equitable proceeding limits. Yes; exclusion incorrect; remand for new lien trial.
Was PCM entitled to enforce the lien given substantial performance questions? Lien enforceable if substantial performance (Nelson rule). Defects may offset or negate lien; relevant to performance. Lien validity requires substantial performance; remand to determine.
Did the district court properly grant summary judgment on the Bells’ counterclaims under NORA? NORA failure warrants dismissal; deadlines rigid. Counterclaims barred, so no defense impact on lien. affirmed; dismissal without prejudice, but remand on lien grounds.
Should attorney fees and costs awarded to PCM be upheld? As lien claimant, PCM entitled to fees if lien enforced. Fees require lien outcome; pending remand affects award. Vacated; fees to be reconsidered on remand.

Key Cases Cited

  • Nelson v. Hazel, 89 Idaho 480, 406 P.2d 138 (Idaho 1965) (substantial performance concept in lien context; attachment vs recovery distinct)
  • Ervin Construction Co. v. Van Orden, 125 Idaho 695, 874 P.2d 506 (Idaho 1993) (components may be defective without destroying overall substantial performance)
Read the full case

Case Details

Case Name: Perception Construction Management, Inc. v. Bell
Court Name: Idaho Supreme Court
Date Published: Jun 29, 2011
Citations: 254 P.3d 1246; 2011 Ida. LEXIS 101; 151 Idaho 250; 36955
Docket Number: 36955
Court Abbreviation: Idaho
Log In