History
  • No items yet
midpage
495 S.W.3d 514
Tex. App.
2016
Read the full case

Background

  • After Hurricane Ike, Chambers County contracted Peleo to rebuild a firehouse funded by FEMA; Amundson Consulting (and Amundson) participated as consultant/representative and Dannenbaum was architect/contract administrator.
  • Peleo submitted three payment applications; Dannenbaum certified 90% of the first two and never certified the third; Chambers County paid the certified amounts but withheld the uncertified 10% on the first two and made no payment on the third.
  • On October 28, 2010, Amundson told Peleo to stop work, allegedly stating FEMA ordered a stop; Dannenbaum sent a stop-work letter; 40 days later Dannenbaum told Peleo to resume and Peleo responded by terminating the contract.
  • Peleo sued Chambers County, Dannenbaum, Amundson, and Amundson Consulting asserting breach of contract, Prompt Payment Act, fraudulent and negligent misrepresentation; Dannenbaum was dismissed earlier for lack of certificate of merit.
  • The trial court granted summary judgment for defendants on liability (including Chambers County and Amundson Consulting) and later, after a jury awarded damages to Chambers County, granted JNOV and rendered a larger verdict plus attorneys’ fees; this appeal and rehearing followed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether trial court erred by summary judgment dismissing Peleo’s breach of contract claim (failure to pay full invoices/retainage) Peleo: County’s withholding of 10% on first two invoices and failure to timely pay constituted prior breach excusing Peleo’s termination County: Only obligated to pay amounts certified by Dannenbaum; withholding authorized by contract/retainage or due to bona fide dispute; immaterial withholding Reversed: summary judgment improper — fact issues exist whether County breached or withholding was authorized/material; Dannenbaum acted as County’s rep so County bears responsibility for certifications
Whether Chambers County proved entitlement to summary judgment on its breach claim (Peleo’s termination breached) Peleo: Prior County breach excused Peleo’s termination County: Peleo’s termination was a material breach; withholding was immaterial or authorized; procedural/contract remedies not followed by Peleo Reversed: County did not establish liability as matter of law; fact issues remain on withholding, notice, and materiality
Whether summary judgment on Peleo’s Prompt Payment Act claim was proper Peleo: Late partial payments and partial withholdings triggered interest/violations; no timely 21-day notice of bona fide dispute County: Payments were timely after Dannenbaum certification; bona fide dispute existed; third invoice invalid because sent with termination Reversed: summary judgment improper — statute imposes strict deadlines; County produced no 21-day dispute notices; evidence raises Prompt Payment Act issues
Whether summary judgment for Amundson/Amundson Consulting on fraudulent/negligent misrepresentation claims was proper Peleo: Amundson falsely represented FEMA funding/stop order; Peleo justifiably relied when bidding and during performance Amundson: Claims fail because Peleo’s contract breach precludes reliance, statements were not false or were County statements merged into contract Reversed: summary judgment improper — factual issues on falsity, knowledge, reliance, intent, and merger clause does not bar fraud per Italian Cowboy doctrine
Whether attorneys’ fees and JNOV award should stand Peleo: If liability reversed, JNOV and fee award must also be reversed County: Award proper because it prevailed on liability below Reversed: Because liability rulings reversed, remand required and damages/JNOV/fees reversed as well

Key Cases Cited

  • MMP, Ltd. v. Jones, 710 S.W.2d 59 (Tex. 1986) (movant must conclusively establish right to summary judgment)
  • City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005) (legal-sufficiency standard and reviewing evidence in light most favorable to nonmovant)
  • Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195 (Tex. 2004) (prior material breach excuses further performance)
  • Mann Frankfort Stein & Lipp.Advisors, Inc. v. Fielding, 289 S.W.3d 844 (Tex. 2009) (de novo review of summary judgment)
  • King Ranch, Inc. v. Chapman, 118 S.W.3d 742 (Tex. 2003) (no-evidence standard and scintilla rule)
  • Italian Cowboy Partners, Ltd. v. Prudential Ins. Co. of Am., 341 S.W.3d 323 (Tex. 2011) (merger clauses do not generally bar fraudulent inducement claims)
Read the full case

Case Details

Case Name: Pelco Construction Co. v. Chambers County
Court Name: Court of Appeals of Texas
Date Published: May 12, 2016
Citations: 495 S.W.3d 514; 2016 Tex. App. LEXIS 5047; 2016 WL 2936403; NO. 01-14-00317-CV
Docket Number: NO. 01-14-00317-CV
Court Abbreviation: Tex. App.
Log In
    Pelco Construction Co. v. Chambers County, 495 S.W.3d 514