History
  • No items yet
midpage
Parkway Construction Services, Inc., Respondent/Cross-Appellant v. Blackline LLC d/b/a Blackline Design and Construction, and Magnolia Halliday, LLC
573 S.W.3d 652
Mo. Ct. App.
2019
Read the full case

Background

  • Parkway (plumbing subcontractor) contracted with Blackline (general contractor) to renovate two apartment buildings; contract price $96,000 and Blackline agreed to supply certain fixtures. Parkway agreed to rework plumbing and to replace up to a 50% threshold of DWV piping; work beyond that required a written change order.
  • Dispute arose when Parkway replaced substantially more DWV stacks (all 43 stacks) without a written change order; Parkway sought extra payment for work alleged to be outside the contract.
  • Parkway stopped work after Blackline refused retroactive change-order approval; Blackline hired another plumber to finish the job and tendered a final conditional payment of $8,712.97 which Parkway refused.
  • Parkway signed a partial lien waiver and accepted $25,200 covering work through June 16, 2015; Parkway later sued asserting breach of contract (reinstated after voluntary dismissal) and equitable claims (unjust enrichment, quantum meruit) seeking ~$103,449 total.
  • Trial court awarded Parkway $9,763.97 (contract recovery: $8,712.97 plus $1,051 for shower-valve work) and found Parkway the prevailing party, awarding $103,234.31 in attorneys’ fees; denied equitable claims as waived/released by the lien waiver.

Issues

Issue Plaintiff's Argument (Parkway) Defendant's Argument (Blackline) Held
Whether trial court could "reinstate" Count III (breach) after Parkway voluntarily dismissed it without prejudice Parkway: dismissal was without prejudice; court retained authority to allow reassertion before trial and no prejudice resulted Blackline: dismissal terminated the claim and court lost authority; reinstatement was impermissible Court: Affirmed — court did not abuse discretion; reinstatement/amendment was allowed because dismissal was without prejudice and caused no prejudice
Whether trial court erred in awarding $1,051 for shower-valve work not pleaded as breach of contract / whether it was tried by consent Parkway: shower-valve work was part of extra-work claims and/or tried by consent; Blackline had approved change order Blackline: shower-valve payment was pleaded only under equitable claims; it was not litigated as a breach by consent Court: Reversed as to the shower-valve award — trial court erred in treating that item as tried by consent and awarding it in Count III
Whether Parkway was the prevailing party and entitled to contractual attorneys’ fees; and whether fee award was excessive Parkway: prevailed on main issue (payment for work) and is entitled to fees for litigation arising out of contract Blackline: Parkway lost principal equitable claims (which were main issues) and thus should not be prevailing party; fee award disproportionate Court: Parkway is the prevailing party (obtained some contract relief on the main payment dispute) and entitled to fees, but remanded to recalculate fees excluding amounts exclusively attributable to unsuccessful equitable claims (including shower-valve work)
Whether equitable claims (unjust enrichment, quantum meruit) survive given contract change-order clause and lien waiver Parkway: equitable recovery permissible for extra work; waiver ambiguous and lacked consideration Blackline: extra work required written change order; Parkway signed lien waiver and released claims through June 16, 2015 Court: Affirmed — equitable claims barred: contract required written change orders and Parkway’s claims for extra work were released by the unambiguous lien waiver supported by consideration

Key Cases Cited

  • Richter v. Union Pac. R.R. Co., 265 S.W.3d 294 (Mo. App. E.D. 2008) (discusses effect of voluntary dismissal and court authority to reinstate claims)
  • Diehl v. Fred Weber, Inc., 309 S.W.3d 309 (Mo. App. E.D. 2010) (standard for abuse of discretion on amendment of pleading)
  • Buckhannon Bd. & Care Home, Inc. v. W. Va. Dep’t of Health & Human Res., 532 U.S. 598 (U.S. 2001) (definition of "prevailing party" as one in whose favor judgment is rendered)
  • Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976) (standard of review for court-tried cases)
  • Herbert & Brooner Constr. Co. v. Golden, 499 S.W.2d 541 (Mo. App. K.C.D. 1973) (rule that written change-order requirement bars recovery for extra work absent writing or waiver)
  • Tharp v. Keeter/Schaefer Invs., L.P., 943 S.W.2d 811 (Mo. App. S.D. 1997) (lien waiver validity requires consideration or detrimental reliance)
Read the full case

Case Details

Case Name: Parkway Construction Services, Inc., Respondent/Cross-Appellant v. Blackline LLC d/b/a Blackline Design and Construction, and Magnolia Halliday, LLC
Court Name: Missouri Court of Appeals
Date Published: Mar 26, 2019
Citation: 573 S.W.3d 652
Docket Number: ED106326
Court Abbreviation: Mo. Ct. App.