midpage
Projects
Sign in to see your projects.
2015 Ohio 3478
Ohio Ct. App.
2015
Read the full case

Background

  • Bridgeview Crossing, LLC owned a shopping-center project; Snider-Cannata Interests (SCI) acted as agent. Panzica was contracted as construction manager and began visible work on December 12, 2006.
  • Huntington National Bank made a construction/open-end loan to Bridgeview, recorded an original mortgage (Nov. 22, 2006) and later recorded several modifications adding parcels to the mortgage.
  • Panzica claimed it was unpaid and filed mechanic’s lien affidavits (initially Oct. 14, 2008; amended Dec. 12, 2008) asserting priority over portions of the property added by later mortgage modifications.
  • Huntington’s loan was later assigned to Garfield Hope, which asserted mortgage priority; Panzica sought foreclosure of its mechanic’s lien and declaratory relief; cross-claims followed.
  • The trial court granted summary judgment to Panzica, holding modifications were junior to Panzica’s lien; Garfield Hope appealed. The appellate court reversed in part, affirmed in part, and remanded for further factual determination.

Issues

Issue Plaintiff's Argument (Panzica) Defendant's Argument (Garfield Hope) Held
Validity of Panzica’s lien given lien waivers Waivers were partial/for particular payments and did not waive lien priority; priority date of first visible work (12/12/2006) preserved. Waivers (several) unconditionally released lien rights, defeating lien or its priority. Genuine issue of material fact exists: some waivers were unconditional partial waivers (April 3 & 11, 2007) and waived claims through those dates; other waivers ambiguous—remand to assess effect on claimed amount.
Necessity of notice of furnishing after notice of commencement Panzica was original contractor/construction manager in privity with owner; thus not required to timely file notice of furnishing. Panzica was not in privity with Bridgeview (contract named SCI), so required to file notice within 21 days; failure defeats priority for work after commencement. Panzica was in privity with Bridgeview (agency, contract amendments, and notice of commencement support this); notice of furnishing failure does not bar its lien rights.
Whether mortgage modifications relate back to original mortgage date for priority Modifications take effect when recorded; they do not relate back; thus later-recorded mods are junior to mechanic’s liens filed after original mortgage. Original mortgage was open-end and construction mortgage; modifications incorporate original mortgage and thus relate back (retain senior priority). Modifications do not "relate back" to the original mortgage date; priority of modifications is measured from their recording dates.
Whether mortgage modifications have super-priority under R.C. 1311.14 Each modification must itself include the §1311.14 covenant to get super-priority. Modifications incorporate the original mortgage and its §1311.14 covenant by reference, and thus have super-priority if funds were disbursed in statutory manner. Modifications incorporate the original construction-mortgage covenant by reference and may have super-priority, but genuine factual dispute exists whether loan disbursements complied with §1311.14(B); remand for proof of proper disbursement.

Key Cases Cited

  • Safeco Ins. Co. of Am. v. White, 122 Ohio St.3d 562 (2009) (contract ambiguities are construed against drafter when parties are of equal bargaining power)
  • Wayne Bldg. & Loan Co. v. Yarborough, 11 Ohio St.2d 195 (1967) (mechanic’s lien effective date tied to first visible work)
Read the full case

Case Details

Case Name: Panzica Constr. Co. v. Bridgeview Crossing, L.L.C.
Court Name: Ohio Court of Appeals
Date Published: Aug 27, 2015
Citations: 2015 Ohio 3478; 39 N.E.3d 529; 102233
Docket Number: 102233
Court Abbreviation: Ohio Ct. App.
Log In