267 F. Supp. 3d 205
D.D.C.2017Background
- HQ Hotel contracted with Hensel Phelps as prime contractor to build the Marriott Marquis; Hensel Phelps subcontracted work to Truland, which sub‑subcontracted telecommunications/security work to Paige.
- Hensel Phelps required Truland to obtain a private Payment Bond from XL (with related sureties) guaranteeing payment to laborers/suppliers if Truland failed to pay.
- Truland went bankrupt; Paige incurred storm‑remediation, acceleration, and pending change‑order costs and filed a claim under the Payment Bond and sued XL for unpaid sums.
- After a six‑day bench trial, the Court found XL liable under the Bond but reduced some claimed damages (including a 50% reduction for insufficient proof) and credited payments XL had already made, awarding Paige $463,092.50.
- Paige moved to amend the damages calculation, requested prejudgment interest, and sought attorney fees; the Court heard post‑trial briefing and issued the memorandum opinion resolving those motions.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Court should amend its damages calculation (reduce 50% discount; reverse credit for SPL settlement) | The 50% reduction was improperly applied to storm and pending PCO claims; SPL credit was improper | The trial court properly exercised fact‑finding discretion given Paige’s deficient records; SPL credit was correct | Denied—Court affirmed its factual discount and credit decisions as reasonable exercise of its fact‑finding role |
| Whether Paige is entitled to prejudgment interest on the damages award | Prejudgment interest should be awarded to compensate deprivation of use of funds withheld since claim accrued | XL argued uncertainty of the amount owed (due to Paige’s poor recordkeeping) counsels against interest | Granted in part—Court awarded simple prejudgment interest at 6% (D.C. statutory rate), totaling $83,813.40, for a combined award of $546,905.90 |
| Whether Paige may recover attorney fees from XL under the Payment Bond | The Bond should be read coextensive with Truland’s obligations to Paige (which include a fee‑shifting clause), so fees are recoverable | The Bond is a private common‑law instrument that limits recovery to "amounts due for labor, material or equipment" and contains no fee provision | Denied—Court held the Bond’s text does not cover attorney fees and declined to import the Sub‑subcontract’s fee clause into the Bond |
Key Cases Cited
- West Virginia v. United States, 479 U.S. 305 (establishes distinction between pre‑ and post‑judgment interest)
- Kaiser Aluminum & Chemical Corp. v. Bonjorno, 494 U.S. 827 (post‑judgment interest runs from entry of judgment)
- House of Wines, Inc. v. Sumter, 510 A.2d 492 (D.C. 1986) (D.C. Code § 15‑109 affords courts broad discretion to award prejudgment interest)
- Hensley v. Eckerhart, 461 U.S. 424 (fee applicant bears burden to establish entitlement to attorney fees)
- United States ex rel. Sherman v. Carter, 353 U.S. 210 (Miller Act bonds construed liberally to protect laborers and suppliers)
- Purcell v. Thomas, 28 A.3d 1138 (D.C. 2011) (contract language controls; cannot imply liability beyond contract terms)
- Goldberg, Marchesano, Kohlman, Inc. v. Old Republic Sur. Co., 727 A.2d 858 (D.C. 1999) (scope of surety liability measured by bond terms)
- Estate of Dickson v. [unknown], 736 A.2d 1007 (D.C. 1999) (surety liability not to be extended by implication)
- Tri‑State Employment Services, Inc. v. Mountbatten Surety Co., 295 F.3d 256 (2d Cir. 2002) (surety bond construed with principal contract; liability coextensive with principal‑obligee obligations)
