Padgett v. City of Monte Sereno
5:04-cv-03946
N.D. Cal.Oct 7, 2019Background
- In 2004 Padgett sued multiple defendants under § 1983; at trial he prevailed only on a First Amendment retaliation claim and recovered nominal and reduced punitive damages.
- McManis Faulkner withdrew in 2006; Padgett was pro se until Kallis & Bustamante became counsel in Sept. 2008 and represented him until relieved in July 2013.
- Padgett signed a hybrid fee agreement with Kallis & Bustamante providing for a modified contingency (20% of award), lodestar entitlement for trial work, and a contractual lien on any recovery.
- The district court (2015) awarded $471,056.64 in attorneys’ fees and $100,000 in costs directly to Kallis & Bustamante; Padgett appealed only the allocation of fees to counsel.
- The Ninth Circuit vacated and remanded, instructing the district court to determine whether contractual provisions or an attorney lien justified paying fees to counsel rather than to the plaintiff.
- This court held the fee agreement was voidable (not void) under Cal. Bus. & Prof. Code § 6147 but remained in effect on the March 31, 2015 award date (Padgett voided it in Jan. 2017), so the contractual assignment justified awarding fees directly to the firms; the 2015 award was reinstated.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether attorney fees awarded by the district court could be paid directly to counsel rather than to Padgett | Padgett argued fees belong to the plaintiff under federal law and the award to counsel was improper | Kallis & Bustamante argued the fee agreement and contractual lien assigned fees to counsel, authorizing direct payment | Held: Contract was effective on the award date, so the contractual assignment justified paying fees to counsel |
| Whether a state-court judgment declaring the contract void precludes this court from deciding the contract issue (res judicata) | Padgett relied on the state-court ruling that later found the agreement void | Firms argued the state-court judgment was not final for res judicata because it was on appeal | Held: California law treats a trial-court judgment as non-final while appeal is pending; no claim-preclusion effect here |
| Whether the hybrid fee agreement complied with Cal. Bus. & Prof. Code § 6147 (valid vs. void) | Padgett argued noncompliance with § 6147 rendered the agreement void and unenforceable | Firms acknowledged § 6147 noncompliance but argued noncompliance makes the agreement voidable, not void, so enforceable until client voids | Held: § 6147 noncompliance made the contract voidable; Padgett did not void it until Jan. 24, 2017, so it was enforceable in Mar. 2015 |
| Whether the fee award constituted lodestar/award category covered by the contract | Padgett did not challenge the reasonableness of the award, only the payee | Firms argued the award was a lodestar allotment and within the contract’s scope | Held: The court’s 2015 lodestar award falls within the contract’s terms; fees properly awarded to counsel |
Key Cases Cited
- Pony v. County of Los Angeles, 433 F.3d 1138 (9th Cir.) (prevailing party, not attorney, holds statutory right to seek § 1988 fees)
- United States v. $186,416.00 in U.S. Currency, 642 F.3d 753 (9th Cir.) (absent contract or lien, fee awards go to the prevailing party)
- Gilbrook v. City of Westminster, 177 F.3d 839 (9th Cir.) (§ 1988 requires fee awards be made to prevailing party absent contractual assignment)
- Padgett v. Loventhal, 706 F.3d 1205 (9th Cir.) (vacating district court order for inadequate explanation of fee award)
- Semtek Int’l Inc. v. Lockheed Martin Corp., 531 U.S. 497 (U.S.) (federal courts apply state claim-preclusion law to state-court judgments)
- Yvanova v. New Century Mortgage Corp., 365 P.3d 845 (Cal.) (distinction between void and voidable contracts)
