738 F.3d 192
9th Cir.
2013
Read the full case

Background

  • Measure C in Huntington Beach required voter approval for city-owned park structures costing over threshold, codified as charter § 612(b).
  • T-Mobile obtained planning/building permits and signed Site License Agreements to install antennae in Harbour View Park and Bolsa View Park.
  • Permits were issued in 2007–2009; construction commenced after licenses, but faced public opposition.
  • City later suspended construction, asserting Measure C required voter approval before proceeding; T-Mobile sought federal relief arguing TCA preemption.
  • District court found Measure C preempted and delayed permits; voters later disapproved construction in 2010; case remanded for further proceedings.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the TCA preempts Measure C. T-Mobile argues Measure C regulates wireless facilities and is preempted by § 332(c)(7)(B)(i)/(iv). City contends Measure C is market-participant landowner action not subject to preemption and aligns with procedural TCA limits. Measure C not preempted; outside TCA's scope.
Does the market-participant doctrine shield the city’s actions from preemption? T-Mobile asserts the city acted as regulator, not market participant, so TCA applies. City asserts market participation exempts its actions from preemption. Court did not rely on market-participant exception; still held Measure C outside preemption.
Is Measure C a land-use regulation/decision subject to § 332(c)(7)'s limits? Measure C would affect land-use decisions on wireless facilities. Measure C is a standalone voter approval mechanism unrelated to local zoning/regulatory process. Measure C is outside the TCA’s land-use framework; not preempted.
If preemption applies, do the procedural requirements of § 332(c)(7)(B)(ii)-(iii) apply to Measure C? T-Mobile seeks timely, written, evidence-based decisions; Measure C disrupts that process. Measure C does not implicate adjudicative procedures; it is an owner-approval mechanism. Procedural preemption requirements not triggered by Measure C.
What is the correct remedy on cross-appeal and remand? Permanent injunction to allow construction; direct return to permits. Remand sufficient to align with TCA requirements. Remainder moot; court remanded for proceedings consistent with opinion.

Key Cases Cited

  • Kay v. City of Rancho Palos Verdes, 504 F.3d 803 (9th Cir. 2007) (preserves local land-use authority while limiting federal preemption scope)
  • MetroPCS v. City of San Francisco, 400 F.3d 715 (9th Cir. 2005) (preemption context for wireless facilities; distinguishes nonregulatory actions)
  • Sprint Spectrum L.P. v. Mills, 283 F.3d 404 (2d Cir. 2002) (landowner decisions on property not inherently regulatory; preemption limited)
  • Cellular Tel. Co. v. Town of Oyster Bay, 166 F.3d 490 (2d Cir. 1999) (TCA procedural requirements for adjudicative decisions)
  • City of Rancho Palos Verdes v. Abrams, 544 U.S. 113 (2005) (statutory framework for local land-use vs. federal preemption)
Read the full case

Case Details

Case Name: Omnipoint Communications, Inc. v. City of Huntington Beach
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Dec 11, 2013
Citations: 738 F.3d 192; 2013 WL 6486240; 59 Communications Reg. (P&F) 759; 2013 U.S. App. LEXIS 24610; 17-35634
Docket Number: 17-35634
Court Abbreviation: 9th Cir.
Log In
    Omnipoint Communications, Inc. v. City of Huntington Beach, 738 F.3d 192