midpage
Projects
Sign in to see your projects.
2020 Ohio 4628
Ohio Ct. App.
2020
Read the full case

Background

  • AEP (Ohio Power Co.) planned a 23-mile rebuild of a 69kV transmission line and adopted a Board resolution declaring the Project a public necessity; the reroute around Mount Sterling crossed the Duffs’ 207‑acre parcel and required a ~1.5‑acre easement.
  • AEP and the Duffs negotiated but failed to agree; AEP filed an eminent‑domain appropriation petition under R.C. Chapter 163 on Sept. 4, 2019.
  • The Duffs served discovery seeking AEP siting documents; they claimed AEP’s responses were incomplete and moved to compel, requested a discovery hearing and a continuance of the necessity hearing.
  • The trial court denied the continuance/discovery hearing (after off‑the‑record conference) and held the necessity hearing on Dec. 17, 2019; the court found the Duffs failed to rebut the presumption of necessity created by AEP’s Board resolution and entered judgment for AEP on Jan. 2, 2020.
  • On appeal the Duffs argued (1) denial of discovery/continuance was reversible error, (2) the court evaluated the Project’s necessity rather than the specific easement (and the easement’s breadth exceeded necessity), and (3) AEP grossly abused its routing discretion (no siting study; alternatives not considered).

Issues

Issue Plaintiff's Argument (Duff) Defendant's Argument (AEP) Held
Denial of discovery hearing and continuance of necessity hearing AEP withheld critical siting/Board materials; hearing forced without essential evidence Discovery rules apply but R.C. 163.09 accelerates hearings; parties received supplemental responses and trial court acted within its discretion Affirmed — appellant failed to provide transcript/App.R.9 statement of in‑chamber discussion (presume regularity); statutory scheme favors expedition, no reversible error shown
Court focused on Project necessity rather than specific easement breadth Court improperly relied on Project‑level necessity; easement language is broad (could permit >69kV) and exceeds the declared need Board resolution creates rebuttable presumption; testimony showed higher voltage would require OPSB approval and route choice was justified Affirmed — Duffs failed to rebut presumption; evidence supported necessity for the easement and easement scope did not defeat necessity
Alleged gross abuse of discretion in route selection AEP violated its own siting procedures (no siting study) and did not consider southern alternatives, showing bad faith/gross abuse Cited internal guidance applied to independent developers (not AEP); witnesses testified routing analysis occurred and alternatives were considered and rejected for proximity, cost, and practicality Affirmed — competent, credible evidence showed a reasoned, good‑faith routing decision; no fraud, bad faith, or gross abuse of discretion shown

Key Cases Cited

  • Cleveland Elec. Illum. Co. v. Astorhurst Land Co., 18 Ohio St.3d 268 (1985) (Rule of Civil Procedure discovery applies to appropriation proceedings)
  • State ex rel. Duncan v. Mentor City Council, 105 Ohio St.3d 372 (2005) (eminent domain allowed for public use with just compensation)
  • Myocare Nursing Home, Inc. v. Fifth Third Bank, 98 Ohio St.3d 545 (2003) (rebuttable‑presumption burden‑shifting principles)
  • Giesy v. Cincinnati, Wilmington, and Zanesville R.R. Co., 4 Ohio St. 308 (1854) (necessity for condemnation need not be absolute)
  • Cleveland Electric Illuminating Co. v. Scapell, 44 Ohio App.2d 13 (1975) (appropriating agency must act in a reasoned, good‑faith manner)
  • Masheter v. Benua, 24 Ohio App.2d 7 (1970) (statutory scheme advances appropriation proceedings to minimize delay)
Read the full case

Case Details

Case Name: Ohio Power Co. v. Duff
Court Name: Ohio Court of Appeals
Date Published: Sep 28, 2020
Citations: 2020 Ohio 4628; CA2020-01-004
Docket Number: CA2020-01-004
Court Abbreviation: Ohio Ct. App.
Log In