midpage
Projects
Sign in to see your projects.
2021 Ohio 2714
Ohio Ct. App.
2021
Read the full case

Background

  • Ohio Power (AEP subsidiary) filed eminent-domain petitions to expand/replace existing 23 kV lines with a 138 kV transmission project, seeking broader easements across several landowners’ parcels; the PUCO Siting Board issued a certificate approving the Project and Ohio Power’s board passed a December 2019 resolution approving the Project.
  • Landowners answered, denying necessity and challenging specific easement terms (broad assignability, rights to distribution lines, anti-abandonment clause, herbicide/right-to-exclude concerns) and requested R.C. 163.09(B) necessity hearings.
  • At the consolidated R.C. 163.09 hearing Ohio Power witnesses testified on the Project need, authenticated the December 2019 Board resolution, and admitted distribution-line rights were not needed and could be dropped; testimony also showed an earlier petition verification referenced the later Board resolution.
  • Trial court: (1) denied landowners’ Civ.R. 12(C) motion to dismiss Burns/Bohlen petitions for defective verification (found motion untimely and verification inconsequential), (2) held easements (except distribution-line rights) necessary, concluding the Siting Board and Ohio Power Board created statutory presumptions of necessity, and (3) ordered removal of distribution-line rights but declined to treat that concession as abandonment requiring cost awards.
  • Landowners appealed, challenging (a) denial of judgment on the pleadings re: invalid verification, (b) application of R.C. 163.09(B) presumptions, (c) trial court’s deference to Ohio Power on scope/necessity of easements, and (d) denial of R.C. 163.21(B) relief after distribution-rights were rejected.

Issues

Issue Plaintiff's Argument (Ohio Power) Defendant's Argument (Landowners) Held
1) Motion for judgment on the pleadings: defective petition verification; timeliness under Civ.R. 12(C) Motion was untimely because filed after presentation at necessity hearing ("trial"); verification not false or inconsequential; Civ.R.11 preempts verification requirement Verification was facially false (verification predated Board resolution), motion timely (must be before jury trial on compensation) and defect voids petition Court erred to call motion untimely ("trial" is jury compensation trial), but denial affirmed on merits: verification invalid yet cured by hearing authentication and R.C.163.12(C) amendment power (harmless error).
2) Applicability of R.C.163.09(B) presumptions (board resolution & regulatory approval) Siting Board certificate approving Project and Ohio Power Board resolution establishing Project necessity trigger irrebuttable (regulatory) and rebuttable (board) presumptions; court need not review easement terms Siting Board/Board approved the Project, not the specific appropriations or easement terms; presumptions inapplicable to particular easements Reversed as to application of presumptions: neither the Siting Board nor Ohio Power Board approved the specific easements, so statutory presumptions (both rebuttable and irrebuttable) do not apply to these appropriations.
3) Scope-of-take review and deference to utility on necessity/extent Utility is best positioned to determine what is necessary; scope/extent may be addressed at compensation trial (jury) Trial court must perform a limited but vigilant review under Norwood; extent of appropriation is a matter for the court to define, not deferred to jury or utility Trial court erred by deferring to Ohio Power and failing to review contested easement terms individually; remanded for a R.C.163.09(B) hearing to determine necessity/extent of each challenged term.
4) Abandonment / distribution-line rights and awarding costs under R.C.163.21 Removing distribution rights was not abandonment; no automatic fee award Landowners successfully defeated appropriation of distribution-line rights at the hearing; R.C.163.21(B) requires judgment against agency for costs and just disbursement awards for owners who defended particular property rights Court correctly found no voluntary abandonment, but erred by not awarding costs/disbursements under R.C.163.21(B) after determining Ohio Power was not entitled to appropriate the distribution-line rights; remand to determine just awards.

Key Cases Cited

  • Norwood v. Horney, 853 N.E.2d 1115 (Ohio 2006) (courts must apply vigilant, limited review in eminent-domain cases to ensure the state takes no more than necessary)
  • Cedar Point Nursery v. Hassid, 141 S. Ct. 2063 (U.S. 2021) (the right to exclude is a core stick in the bundle of property rights)
  • Masheter v. Boehm, 307 N.E.2d 533 (Ohio 1974) (extent of the taking is a question of law for the trial court to decide before valuation)
  • State ex rel. New Wen, Inc. v. Marchbanks, 167 N.E.3d 934 (Ohio 2020) (discusses fee awards and Chapter 163 remedial scheme)
  • Horsley v. Essman, 763 N.E.2d 245 (Ohio Ct. App. 2001) (explains effect of rebuttable presumptions and the burden-shifting mechanism)
Read the full case

Case Details

Case Name: Ohio Power Co. v. Burns
Court Name: Ohio Court of Appeals
Date Published: Aug 4, 2021
Citations: 2021 Ohio 2714; 176 N.E.3d 778; 20CA19, 20CA20, 20CA21, 20CA22
Docket Number: 20CA19, 20CA20, 20CA21, 20CA22
Court Abbreviation: Ohio Ct. App.
Log In