History
  • No items yet
midpage
2018 Ohio 4156
Ohio Ct. App.
2018
Read the full case

Background

  • Ohio Edison sued Jeanna Houser after her vehicle damaged one of Edison’s utility poles; Edison sought $6,100.14 in replacement costs (labor, equipment, materials, and a 12.6% ‘‘accounting and general’’ multiplier for indirect costs).
  • Edison supported its summary-judgment motion with company invoices, CREWS system reports, and three affidavits explaining costs, pole age (placed in service 1970), and accounting methodology.
  • Houser conceded fault but disputed the damage calculation: she argued Edison should depreciate the pole and that the indirect-cost multiplier was not proven with reasonable certainty; she submitted an expert affidavit (Hock) to that effect.
  • The trial court granted Edison summary judgment, refused depreciation, allowed indirect costs, and awarded $6,100.01 plus interest.
  • On appeal the Sixth District reviewed de novo and affirmed summary judgment in Edison’s favor but found legal error in (1) failing to apply accrued depreciation to the pole/facilities and (2) awarding indirect costs that lacked reasonable certainty.
  • The court reduced Edison’s award by $238.13 (depreciation of the pole/facilities) and disallowed $692.68 in indirect costs; final judgment was modified to $5,169.33.

Issues

Issue Plaintiff's Argument (Edison) Defendant's Argument (Houser) Held
Whether replacement cost must be reduced by accrued depreciation of the pole/facilities No depreciation; full replacement cost is recoverable Apply straight-line depreciation to the pole and attached facilities (80-year life, pole in service 45 years) Court: Depreciation applies but only to the pole and attached facilities (straight-line). Reduced award by $238.13
Whether Edison may recover indirect (overhead) costs calculated via a company-wide 12.6% multiplier Indirect costs are recoverable where computed under sound accounting principles mandated by regulators Multiplier lacks project-specific allocation; indirect costs not proven with reasonable certainty and thus unrecoverable Court: Indirect costs not proved with reasonable certainty here; disallowed $692.68; majority reverses award of those costs

Key Cases Cited

  • Grafton v. Ohio Edison Co., 77 Ohio St.3d 102 (Ohio 1996) (standard of appellate de novo review of summary judgment)
  • Queen City Terminals v. General Am. Transp. Corp., 73 Ohio St.3d 609 (1995) (economic-loss rule requires direct causal nexus between property damage and indirect economic losses)
  • Floor Craft Floor Covering, Inc. v. Parma Community Gen. Hosp. Assn., 54 Ohio St.3d 1 (1990) (discussion of privity and recoverability of economic losses)
  • Complete Gen. Constr. v. Ohio Department of Transportation, 94 Ohio St.3d 54 (2002) (treatment of indirect costs in public-construction contract delay context)
  • Ohio Power Co. v. Zemelka, 19 Ohio App.2d 213 (7th Dist.) (measure of damages for negligent destruction: reproduction cost less accrued depreciation of pole and attached facilities)
Read the full case

Case Details

Case Name: Ohio Edison Co. v. Houser
Court Name: Ohio Court of Appeals
Date Published: Oct 12, 2018
Citations: 2018 Ohio 4156; E-17-063
Docket Number: E-17-063
Court Abbreviation: Ohio Ct. App.
Log In
    Ohio Edison Co. v. Houser, 2018 Ohio 4156