History
  • No items yet
midpage
204 Conn.App. 614
Conn. App. Ct.
2021
Read the full case

Background

  • O&G Industries supplied concrete to subcontractor Concrete Superstructures, Inc. (CSS) on an 18‑story Stamford project; CSS then failed to pay $484,919.30 owed for deliveries between Sept.–Dec. 2016.
  • O&G had previously billed the general contractor (Morganti) under a joint check arrangement and was paid for earlier deliveries; later O&G opened a credit account for CSS (for another project) and billed CSS directly for the disputed deliveries.
  • O&G filed a timely mechanic’s lien; the surety (American Home Assurance Co.) issued a substitute bond under Conn. Gen. Stat. §49‑37, which O&G accepted; O&G also submitted a claim under the project payment bond issued by the surety for Morganti.
  • The surety denied the claims and pled nine special defenses (including reckless/bad‑faith conduct by O&G, failure to satisfy a payment‑bond condition precedent by not producing a written contract/purchase order, mitigation/estoppel, and statutory writing requirements).
  • The trial court entered judgment for O&G on both the substitute bond and payment bond claims, finding the surety failed to prove its equitable defenses and that O&G satisfied the payment‑bond claim requirements; the surety appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether O&G’s conduct (giving CSS an account, not immediately suing) breached a duty of "diligence and utmost good faith" (recklessness/bad faith) O&G acted reasonably: it took protective steps (sought joint‑check agreement, returned redacted lien waiver), was not the party that brought CSS onto project, and CSS appeared judgment‑proof later. Surety: O&G acted recklessly/unfairly by extending an account and failing to mitigate, so surety discharged from liability. Trial court’s factual findings that O&G did not act with common‑law recklessness or bad faith were supported by the record; affirmed.
Whether O&G satisfied the payment bond condition requiring a copy of the claimant’s written contract or purchase order with the subcontractor Invoices, signed delivery tickets, a credit agreement, and price quotations collectively evidenced the agreement and satisfied item 3 of §16.1 of the payment bond. Surety: O&G failed to provide the required written agreement/purchase order; invoices/delivery tickets are insufficient and many were unsigned. Court reasonably construed the bond and found the submitted invoices/delivery tickets and related documents satisfied the condition precedent; affirmed.
Whether O&G could recover damages exceeding the penal sum of the substitute bond (including prejudgment and offer‑of‑compromise interest) O&G sought full recovery of the unpaid balance plus statutory interest and offer‑of‑compromise interest; it filed an offer of compromise that defendant did not accept. Surety argued the award exceeded the substitute bond’s penal sum and challenged interest calculations. Appellate court declined to reach merits: defendant waived this claim by failing to object at trial to the court’s interest/calculation determinations.
Whether the trial court abused its discretion by allowing O&G rebuttal evidence after the surety rested without calling witnesses O&G limited rebuttal to evidence presented during the surety’s cross‑examination and documents admitted by the surety; the court had previously barred such evidence in O&G’s case‑in‑chief. Surety: No case was presented to rebut because it called no direct witnesses; rebuttal was improper. Trial court did not abuse discretion. Rebuttal was properly limited to refuting evidence the surety elicited/admitted during cross‑examination.

Key Cases Cited

  • Aetna Bank v. Hollister, 55 Conn. 188 (1886) (historic statement that a claimant must observe diligence and "utmost good faith" when claiming against a surety)
  • Wolthausen v. Trimpert, 93 Conn. 260 (1919) (early treatment of "utmost good faith" and negligence benchmark)
  • Pacelli Bros. Transportation, Inc. v. Pacelli, 189 Conn. 401 (1983) (equating "utmost good faith" with fair dealing in contract contexts)
  • Capstone Building Corp. v. American Motorists Ins. Co., 308 Conn. 760 (2013) (principles for breach of the implied covenant of good faith and fair dealing)
  • Boone v. Boehringer Ingelheim Pharm., Inc., 335 Conn. 547 (2020) (trial court discretion on admission of rebuttal evidence)
  • State v. Lisella, 187 Conn. 335 (1982) (permitting rebuttal evidence where defendant’s cross‑examination effectively raised evidence to be refuted)
  • Williams v. Housing Authority, 327 Conn. 338 (2017) (definition and standard for common‑law recklessness)
Read the full case

Case Details

Case Name: O & G Industries, Inc. v. American Home Assurance Co.
Court Name: Connecticut Appellate Court
Date Published: May 18, 2021
Citations: 204 Conn.App. 614; 254 A.3d 955; AC43135
Docket Number: AC43135
Court Abbreviation: Conn. App. Ct.
Log In
    O & G Industries, Inc. v. American Home Assurance Co., 204 Conn.App. 614