History
  • No items yet
midpage
884 F.3d 1176
D.C. Cir.
2018
Read the full case

Background

  • NorthWestern, a Montana utility, formerly purchased 60 MW of regulation service and passed costs to customers under Schedule 3; it built the 150 MW Dave Gates Generating Station (three 50 MW units) to supply regulation service beginning 2011.
  • NorthWestern proposed a revised Schedule 3 rate to recover Gates Station costs by allocating 45 MW (wind-related) to retail customers at state rates and 60 MW (fuel-related) to retail+wholesale under Schedule 3, using a ratio of 60/105 (.57).
  • NorthWestern’s proposed Schedule 3 also sought to recover fuel costs, credit off-system sales revenue, recover costs from a 2012 three-month outage, and allow recovery for future outage purchases.
  • An ALJ reduced NorthWestern’s proposed rate: used a numerator of 19 MW (excluding regulation-down capacity), a denominator of 150 MW (nameplate), excluded fuel costs from Schedule 3, and required separate filings for outage-related recovery.
  • FERC affirmed the ALJ, ordered refunds of amounts collected in excess of the approved Schedule 3 rate, and NorthWestern petitioned for review under the arbitrary-and-capricious standard.

Issues

Issue NorthWestern's Argument FERC's/Respondent's Argument Held
Whether FERC could exclude regulation-down capacity from numerator Excluding regulation-down was improper; those MWs are needed and were previously passed through (60 MW embedded) NorthWestern failed to show it could not recover by off-system sales or other means; burden on NorthWestern under §205 FERC reasonably excluded regulation-down MWs (numerator reduced to 19)
Whether denominator should be 105 MW or nameplate 150 MW Denominator should be actual MW devoted to regulation (105) Precedent uses nameplate capacity to reflect total available capacity; Gates nameplate = 150 MW FERC reasonably used 150 MW denominator
Whether fuel costs may be recovered under Schedule 3 Fuel costs incurred providing regulation at Gates should be allowed under Schedule 3; retroactive recovery under Schedule 4 may be unavailable Fuel normally recovered under Schedule 4 (energy), Schedule 3 governs capacity; NorthWestern never tried Schedule 4 recovery FERC reasonably excluded fuel costs from Schedule 3 and adequately explained its decision
Whether refunds and separate filings for outage costs were arbitrary Ordering refunds and requiring separate §205 filings for outage-related costs was improper; equitable factors and retroactive recovery concerns insufficiently considered This was an over‑collection case for Schedule 3 customers; refunds are standard; outage and future-purchase recovery require separate factual showings FERC reasonably ordered refunds and required separate filings for outage/future purchase recovery

Key Cases Cited

  • Alabama Electric Cooperative, Inc. v. FERC, 684 F.2d 20 (D.C. Cir. 1982) (just-and-reasonable rate must reflect cost of service plus fair return)
  • FPC v. Hope Natural Gas Co., 320 U.S. 591 (U.S. 1944) (rate-of-return standard and just-and-reasonable principle)
  • Public Service Commission of New York v. FERC, 642 F.2d 1335 (D.C. Cir. 1980) (burden allocation for rate changes vs. constant elements)
  • Kansas Gas & Electric Co. v. FERC, 758 F.2d 713 (D.C. Cir. 1985) (utility proposing a clause that departs from status quo bears burden of proof)
  • Black Oak Energy, LLC, 139 FERC ¶ 61,111 (FERC 2012) (discussion of refunds in over-collection vs. cost-allocation cases)
Read the full case

Case Details

Case Name: Nw. Corp. v. Fed. Energy Regulatory Comm'n
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Mar 16, 2018
Citations: 884 F.3d 1176; No. 16-1176
Docket Number: No. 16-1176
Court Abbreviation: D.C. Cir.
Log In
    Nw. Corp. v. Fed. Energy Regulatory Comm'n, 884 F.3d 1176