History
  • No items yet
midpage
125 Fed. Cl. 469
Fed. Cl.
2016
Read the full case

Background

  • NTS (Nova Group/Tutor-Saliba), a joint venture, contracted with NAVFAC to design and build Pier B at Puget Sound Navy Shipyard with a 1,345-day completion term and liquidated damages for delay.
  • KPFF, NTS’s Designer of Record, used ACI 318-05 §10.13.6(a) to analyze global stability; NAVFAC reviewed and approved design submittals and provided 382 review comments none addressing global stability or KPFF’s chosen method.
  • On March 8, 2010 NAVFAC transmitted a BergerABAM memorandum questioning the design’s global stability approach, prompting NTS to stop critical Pier B work and re-evaluate the government‑approved design.
  • During March–May 2010, NTS and KPFF furnished reports, met with the Government, and retained an independent designer who validated KPFF’s method; on May 27, 2010 NAVFAC concluded the design was technically sufficient and NTS resumed work.
  • NTS alleges the Government’s March 8 action constructively changed the contract, causing a work stoppage and later acceleration (with added manpower, equipment, and overtime), and seeks damages for increased costs; NAVFAC denied the claim citing failure to provide written notice within 20 days as required by FAR 52.243-4.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether failure to give written notice within FAR 52.243-4’s 20-day period bars NTS’s constructive change claim NTS: Government had actual knowledge of the stoppage and acceleration, so the 20-day notice requirement should not preclude the claim Gov: Strict enforcement of FAR 52.243-4 requires dismissal for lack of timely written notice; K‑Con compels dismissal Court denied dismissal: plausible allegations that Government had actual notice create an exception to strict 20‑day notice enforcement

Key Cases Cited

  • Aydin Corp. v. Widnall, 61 F.3d 1571 (Fed. Cir. 1995) (Government liable for costs from a constructive change)
  • Bell/Heery v. United States, 739 F.3d 1324 (Fed. Cir. 2014) (elements of a constructive change claim)
  • K-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000 (Fed. Cir. 2015) (20-day notice requirement; recognized exception for government actual/imputed notice)
  • Singer Co. Librascope Div. v. United States, 568 F.2d 695 (Ct. Cl. 1977) (timely notice distinguishes compensable requests from contract-incorporated work)
  • Calfon Constr. Inc. v. United States, 923 F.2d 872 (Fed. Cir. 1990) (contracting officials’ knowledge of operative facts can excuse strict notice compliance)
Read the full case

Case Details

Case Name: Nova group/tutor-saliba v. United States
Court Name: United States Court of Federal Claims
Date Published: Mar 16, 2016
Citations: 125 Fed. Cl. 469; 2016 WL 1056794; 2016 U.S. Claims LEXIS 198; 15-885C
Docket Number: 15-885C
Court Abbreviation: Fed. Cl.
Log In
    Nova group/tutor-saliba v. United States, 125 Fed. Cl. 469