History
  • No items yet
midpage
Nova Casualty Co. v. Turner Construction Co.
335 S.W.3d 698
Tex. App.
2011
Read the full case

Background

  • Turner hired to build cargo facility; subcontract with BOCA for baggage handling system worth $415,000.
  • BOCA obtained a performance bond from Nova (A-311 type) incorporating the subcontract terms.
  • BOCA abandoned the project on December 14, 2004; Turner notified Nova of default on December 15, 2004.
  • Nova investigated via Forcon; Turner completed work and incurred substantial costs; damages potentially exceed the bond penal sum.
  • Trial court granted partial summary judgment in Turner's favor; final judgment awarded $415,000 plus fees and pre-judgment interest.
  • Parties stipulated that Turner did not terminate BOCA to trigger the bond and that damages would exceed the bond if due.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Turner needed to terminate BOCA to trigger the bond Nova: termination required; bond triggers on termination. Turner not required to terminate; default notice suffices to trigger bond. Turner's default notice sufficed; no termination required.
Whether Turner provided reasonable notice of default to Nova Nova failed to timely act; notice insufficient because pre-default actions occurred. Turner gave notice per bond; Nova delayed investigation instead of mitigating. Turner provided reasonable notice; bond remedies were available.
Whether Turner is entitled to attorneys' fees and pre-judgment interest Turner entitled to recover fees and pre-judgment interest as prevailing bond claimant. Challenge to pre-judgment interest on fees paid pre-judgment; may be improper. Trial court’s award upheld; pre-judgment interest on attorney’s fees within discretion.

Key Cases Cited

  • L & A Contracting Co. v. S. Concrete Servs., Inc., 17 F.3d 106 (5th Cir.1994) (notice/termination principles for default under bonds)
  • In re Lyon Fin'l Servs., Inc., 257 S.W.3d 228 (Tex. 2008) (incorporation by reference and contract knowledge in signature/)
  • Vastine v. Bank of Dallas, 808 S.W.2d 463 (Tex. 1991) (strict construction of surety contracts)
  • Wolf Hollow I, L.P. v. El Paso Mktg., L.P., 329 S.W.3d 628 (Tex. App.—Hou. (14th Dist.) 2010) (doctrine on ambiguity and contract terms)
  • L & A Contracting Co. v. S. Concrete Servs., Inc., 17 F.3d 106 (5th Cir.1994) (notice/termination requirements for surety obligations)
Read the full case

Case Details

Case Name: Nova Casualty Co. v. Turner Construction Co.
Court Name: Court of Appeals of Texas
Date Published: Feb 10, 2011
Citation: 335 S.W.3d 698
Docket Number: 14-09-00733-CV
Court Abbreviation: Tex. App.