History
  • No items yet
midpage
Northwest Tennessee Motorsports Park, LLC v. Tennessee Asphalt Company
410 S.W.3d 810
Tenn. Ct. App.
2011
Read the full case

Background

  • Northwest contracted TAC to repave ~700 feet of a drag strip; contract quoted that subgrade and base issues were not included and implied a workmanlike standard by industry practices.
  • TAC performed coring, milled two inches, and proof rolled; moisture in core holes was observed but not deemed indicative of sub-grade failure by TAC's engineers.
  • Soft spots and ground movement were found, leading TAC to offer two options: overrun asphalt or full excavation/replacement of sub-grade.
  • Northwest chose the overrun option; TAC began paving, became stuck, and machinery damaged areas beyond the contract scope (staging/runoff).
  • Testing later showed high sub-grade moisture; Northwest repaired damaged areas with Ford Construction at a cost of $186,803, losing peak-season business.
  • Trial court found TAC breached the implied warranty to warn; appellate court reversed, finding no breach and awarding TAC the contract price of $44,918.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether TAC breached by failing to warn about sub-grade moisture Northwest: duty to warn existed; moisture risk should have been disclosed. TAC: no duty to warn; core moisture did not indicate sub-grade failure; standard practices absent warning obligation. No breach; no duty to warn established.
Whether TAC breached by the workmanlike standard of practice Northwest: TAC's actions fell below industry standard. TAC: evidence showed overrun was standard practice and no breach of workmanlike conduct. No breach; standard industry practice not shown to require different conduct.
Whether Northwest is entitled lost profits damages Northwest: lost profits from season and customer declines should be recoverable. TAC: damages limited to contract-related costs; lost profits not proven with certainty. Lost profits not awarded.
Whether TAC is entitled to contract price under overrun or original terms Northwest: credits/overrun should not keep TAC from liability for full cost. TAC: overrun was permitted; no breach; contract price should be awarded to TAC. TAC entitled to full contract price; judgment credited by court affirmed.
Whether the trial court erred in awarding credits for partial work Northwest objected to credits reducing recoveries. TAC: credits appropriate to reflect partial performance and avoid windfall. Credits upheld; overall judgment reversed in TAC's favor.

Key Cases Cited

  • Planters Gin Co. v. Fed. Compress & Warehouse Co., Inc., 78 S.W.3d 885 (Tenn. 2002) (central contract interpretation standard: parties' intent governs)
  • Bowling v. Jones, 300 S.W.3d 288 (Tenn. Ct. App. 2008) (implied standard of workmanship in absence of explicit contract term)
  • Carter v. Krueger, 916 S.W.2d 932 (Tenn. Ct. App. 1995) (breach of contract requires showing conditions fell below standard industry practices)
  • Allstate Ins. Co. v. Watson, 195 S.W.3d 609 (Tenn. 2006) (contract interpretation and standard of review principles)
Read the full case

Case Details

Case Name: Northwest Tennessee Motorsports Park, LLC v. Tennessee Asphalt Company
Court Name: Court of Appeals of Tennessee
Date Published: Sep 23, 2011
Citation: 410 S.W.3d 810
Docket Number: W2011-00450-COA-R3-CV
Court Abbreviation: Tenn. Ct. App.