730 F.3d 1008
9th Cir.2013Background
- The Northwest Power Act (16 U.S.C. §§ 839–839h) requires the Northwest Power and Conservation Council to adopt a regional conservation and electric power plan and a fish and wildlife program that protects, mitigates, and enhances fish and wildlife while assuring an adequate, efficient, economical, and reliable power supply.
- The Council adopted a fish and wildlife program in 2009 (the 2009 Program) and later adopted the Sixth Northwest Power Plan (the Plan) in 2010, which incorporated the 2009 Program by reference.
- NRIC challenged the Plan, arguing the Council failed to give "due consideration" to fish and wildlife in the power-plan process, omitted a required methodology for quantifying environmental costs and benefits from the draft Plan, and improperly included the Bonneville Power Administration’s (BPA) market-price-based cost estimate of the 2009 Program.
- The Council had not published its Appendix P methodology in the draft Plan (it appeared first in the final Plan) and removed a lower replacement-cost estimate from the draft while retaining BPA’s higher $750–$900 million annual market-price estimate in the final Plan.
- The Ninth Circuit reviewed the Plan under the Administrative Procedure Act (arbitrary and capricious standard), affirmed the Council on the due-consideration claim, but remanded for (1) notice-and-comment on the quantification methodology and (2) reconsideration (with a reasoned record) of including BPA’s market-price cost estimate.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Council failed to give "due consideration" to protection, mitigation, and enhancement of fish and wildlife when adopting the Plan | NRIC: "Due consideration" requires the Council independently re-evaluate and potentially augment fish and wildlife measures (including reexamining the 2009 Program) in light of new conservation/resource estimates | Council: Due consideration is satisfied by incorporating the 2009 Program, analyzing alternative resource scenarios, and assessing new resources’ environmental impacts | Held: Affirmed for Council — due consideration applies mainly to future conservation/resource acquisitions (BPA implementation), and does not require re‑opening the 2009 Program in this Plan |
| Whether the Council violated APA notice-and-comment by omitting the methodology for quantifying environmental costs and benefits from the draft Plan | NRIC: Omission denied public participation on a statutorily required element and was procedurally unlawful | Council: Omission was an "unfortunate error" and harmless because methodology was self-evident or would not have changed outcome | Held: Remand — omission was not shown to be harmless; Council must publish the methodology for public comment and adoption |
| Whether the substantive methodology in Appendix P is arbitrary or inadequate | NRIC: Appendix P fails to provide a rational method for calculating quantifiable environmental costs and benefits | Council: Methodology choice is technical and entitled to deference; court should not substitute its judgment | Held: Not decided on merits — court declined to address substance because procedural remand may alter methodology |
| Whether inclusion of BPA’s market-price cost estimate of the 2009 Program was arbitrary and harmful | NRIC: Inclusion of the $750–$900M estimate (and removal of a lower replacement-cost estimate) was unexplained, arbitrary, and will skew future planning | Council: BPA estimate was informational, had no bearing on Plan development, and its inclusion was not arbitrary | Held: Remand — Council’s unexplained retention of BPA’s higher estimate (and removal of the alternative) was arbitrary; Council must reexamine and support any cost‑estimate choice in the record |
Key Cases Cited
- Nw. Res. Info. Ctr. v. Nw. Power Planning Council, 35 F.3d 1371 (9th Cir. 1994) (background on Power Act purpose and salmon/hydropower conflict)
- Seattle Master Builders Ass’n v. Pac. Nw. Elec. Power & Conservation Planning Council, 786 F.2d 1359 (9th Cir. 1986) (deference to Council methodology choices in power plans)
- Nw. Envtl. Def. Ctr. v. Bonneville Power Admin., 117 F.3d 1520 (9th Cir. 1997) (agency interpretation and Power Act context)
- Aluminum Co. of Am. v. Bonneville Power Admin., 903 F.2d 585 (9th Cir. 1989) (BPA role in implementing Council plans)
- Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary and capricious standard; need for reasoned explanation)
- Sagebrush Rebellion, Inc. v. Hodel, 790 F.2d 760 (9th Cir. 1986) (harmless-error standard in rulemaking)
- Cal. Wilderness Coal. v. U.S. Dep’t of Energy, 631 F.3d 1072 (9th Cir. 2011) (presumption of prejudice and caution applying harmless-error in notice-and-comment context)
- Greater Yellowstone Coalition v. Lewis, 628 F.3d 1143 (9th Cir. 2010) (agency failure to consider an aspect of the problem)
- Kenaitze Indian Tribe v. Alaska, 860 F.2d 312 (9th Cir. 1988) (avoid interpretations that render statutory provisions redundant)
- Ariz. Cattle Growers’ Ass’n v. U.S. Fish & Wildlife, 273 F.3d 1229 (9th Cir. 2001) (record must support agency’s reasoned evaluation)
- Shinseki v. Sanders, 556 U.S. 396 (2009) (burden of showing prejudicial error is not onerous)
