History
  • No items yet
midpage
Northeastern University v. BAE Systems Information and Electronic Systems Integration Inc.
1:13-cv-12497
D. Mass.
Nov 27, 2013
Read the full case

Background

  • Northeastern and BAE entered a cost-reimbursable sub-award in April 2011 to develop a 192-element acoustic receiver array for an NSF grant.
  • The NSF-ONR Development Grant totaled $975,462 with a fixed fee; amendments later increased the project budget to about $1,077,000 and expanded the array to 192 elements.
  • The SOW and amendments contemplated phased tasks under a cost-reimbursable framework, with risk allocation centered on inputs and budget rather than a fixed price.
  • In 2013, BAE delivered a 64-element sub-array for sea-testing instead of the full 192-element Array, and Northeastern alleges the subarray failed to function properly.
  • Budget exhaustion led BAE to suspend work in June 2013; after disputes over payments, Northeastern filed suit in October 2013 seeking, among other things, a fully functioning array and damages.
  • The court granted in part BAE’s partial motion to dismiss and denied Northeastern’s motion for a preliminary injunction seeking delivery of a fully functioning array by January 15, 2014.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Contract interpretation: is the Agreement cost-reimbursable? Northeastern contends the contract targets a fixed price for a fully functioning array. BAE argues the contract is cost-reimbursable, focusing on inputs and budgeted costs rather than a fixed output. The court finds the Agreement unambiguously cost-reimbursable.
Did BAE breach by failing to deliver a fully functioning 192-element Array within budget? Northeastern asserts BAE must deliver a fully functioning 192-element Array for the agreed budget. BAE maintains it is not obligated to deliver a fixed-output product beyond budget under a cost-reimbursable contract. Count I is dismissed to the extent it seeks delivery of a fully functioning array within a fixed budget.
Whether best-efforts language is implied in a cost-reimbursable contract and governs performance. Northeastern argues BAE failed to use best efforts to complete the project. BAE contends best efforts are implicit in cost-reimbursable contracts and focus on input, not a fixed output. The contract is consistent with cost-reimbursable form; no requirement to fix a price but best efforts may be present.
Northeastern’s motion for a preliminary injunction seeking a fully functioning array by a set date. Northeastern seeks mandatory relief to compel delivery by January 15, 2014. BAE argues against mandatory injunctive relief given the contract structure and likelihood of success. Preliminary injunction denied.

Key Cases Cited

  • Bell Atl. Corp. v. Twombly, 550 U.S. 544 (U.S. 2007) (pliability of pleading requires plausible claims, not mere possibility)
  • Ashcroft v. Iqbal, 556 U.S. 662 (U.S. 2009) (pleadings must contain more than mere conclusory statements)
  • Langadinos v. Am. Airlines, Inc., 199 F.3d 68 (1st Cir. 2000) (accepts allegations as true for motion-to-dismiss standard)
  • Bank v. Int’l Bus. Mach. Corp., 145 F.3d 420 (1st Cir. 1998) (contract interpretation and ambiguity principles in First Circuit)
  • Samia Cos. LLC v. MRI Software LLC, 898 F. Supp. 2d 326 (D. Mass. 2012) (extrinsic evidence allowed to resolve contract ambiguity)
Read the full case

Case Details

Case Name: Northeastern University v. BAE Systems Information and Electronic Systems Integration Inc.
Court Name: District Court, D. Massachusetts
Date Published: Nov 27, 2013
Docket Number: 1:13-cv-12497
Court Abbreviation: D. Mass.