History
  • No items yet
midpage
North Arizona Construction Company
ASBCA No. 61028
A.S.B.C.A.
Dec 11, 2017
Read the full case

Background

  • Contract (W5K9UR-12-P-7021) between North Arizona Construction and the Army for police station upgrades in Afghanistan (May 21, 2012). FAR disputes clause incorporated.
  • Appellant alleged materials were stolen because it could not store them on site; submitted a "Memo for Record" and invoice initially on Oct 27, 2012, and later a formal claim (Nov 27, 2012) for 1,071,444 Afghani (~less than $100,000).
  • Contracting Officer MSgt. Bastiani issued a final decision dated Feb 26, 2013 (digitally signed Mar 1, 2013) denying the claim for lack of support and including standard 90‑day appeal language.
  • Government contends decision was sent/received on Mar 1, 2013; appellant engaged in email exchange thereafter but did not file an appeal until Jan 29, 2017.
  • Board found the government proved receipt (CO declaration and post‑decision email threads), the decision contained adequate appeal instructions, and the 90‑day statutory appeal period was not tolled — appeal dismissed for lack of jurisdiction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Board has jurisdiction because appellant timely appealed CO's final decision Appellant says it lacked knowledge of ASBCA procedure and was not adequately informed; therefore delay excusable Government says appellant received the Feb 26/Mar 1, 2013 final decision with proper appeal language and did not timely appeal within 90 days Held: No jurisdiction — appeal untimely; receipt proven as Mar 1, 2013 and 90‑day CDA period not tolled
Whether the CO's final decision adequately informed appellant of appeal rights Appellant contends inadequate notice / lack of understanding of rights justified late filing Government points to verbatim FAR‑prescribed appeal language in the final decision Held: Decision’s appeal language was adequate; no prejudice shown to justify tolling
Whether post‑decision communications tolled the 90‑day period Appellant suggests government communications left uncertainty about process Government notes CO repeatedly stated decision was final and requested releases — no indication of reconsideration Held: No tolling — emails show CO maintained decision was final; Guardian Angels circumstances (reconsideration) not present
Burden of proof on receipt date Appellant implicitly disputes actual receipt timing Government must show objective indicia of receipt; here offers CO declaration and later references Held: Government met its burden of proving receipt date (objective indicia and appellant’s later conduct consistent with receipt)

Key Cases Cited

  • Decker & Co. v. West, 76 F.3d 1573 (Fed. Cir. 1996) (prejudice or detrimental reliance required to excuse defective appeal notice)
  • Riley & Ephriam Construction Co. v. United States, 408 F.3d 1369 (Fed. Cir. 2005) (government must provide objective indicia to prove contractor received final decision)
  • Guardian Angels Medical Service Dogs, Inc. v. United States, 809 F.3d 1244 (Fed. Cir. 2016) (CO indication of willingness to reconsider can create tolling-like effect if it leads contractor to reasonably delay appeal)
Read the full case

Case Details

Case Name: North Arizona Construction Company
Court Name: Armed Services Board of Contract Appeals
Date Published: Dec 11, 2017
Docket Number: ASBCA No. 61028
Court Abbreviation: A.S.B.C.A.