History
  • No items yet
midpage
178 So. 3d 1061
La. Ct. App.
2015
Read the full case

Background

  • E & Pco International (operator) signed a standard Daywork drilling contract with NorAm Drilling (contractor) on Dec. 7, 2007 for a one-year term and a $22,500/day rate (with mobilization/escrow Exhibit A attached). NorAm was to provide a Super Single rig.
  • E & Pco lacked funding and never deposited funds into the escrow; NorAm nonetheless kept rigs and crews available in Houston. NorAm began proposing a reduced standby rate as an alternative.
  • Parties exchanged emails in Feb. 2008 memorializing a $15,000/day standby rate (the “Email Agreement”), with NorAm charging from Feb. 11, 2008. NorAm issued monthly invoices; E & Pco paid nothing.
  • June 25–26, 2008 letter exchange (the “Letter Agreement”) included NorAm’s statement that the Daywork Contract was “in full force and effect” and Edwards’ signed “Acknowledged and Agreed.” E & Pco later used another contractor after securing financing.
  • NorAm sued for unpaid standby charges (~$4.9M claim). The trial court found the Daywork Contract effective Feb. 11, 2008, awarded $2,010,000 (standby rate Feb. 11–June 25), interest, and attorneys’ fees. E & Pco appealed.

Issues

Issue Plaintiff's Argument (NorAm) Defendant's Argument (E & Pco) Held
Whether the unsigned Addendum (conditioning contract on $1M deposit) was part of the contract Addendum is not part of the contract; Daywork + Exhibit A control The Addendum (or escrow condition) prevented formation/commencement without deposit Court: Addendum was drafted by E & Pco, unsigned by NorAm, and not part of the contract — reject E & Pco’s claim
Effect of the Escrow Clause (Exhibit A) and whether failure to fund voided obligations Escrow clause was part of contract but NorAm waived the strict deposit requirement by conduct E & Pco: Escrow was a condition precedent; without funding there was no obligation Court: Escrow clause did not create an enforceable condition precedent preventing contract; NorAm waived it by subsequent conduct
Whether Feb. 21, 2008 emails constituted agreement to begin charges effective Feb. 11 (Email Agreement) Emails confirmed standby arrangement and effective start date; NorAm relied on them E & Pco: Emails were tentative, only reduced rate, did not activate the contract Court: Emails reasonably show agreement to standby at $15,000/day from Feb. 11; E & Pco’s acknowledgement did not dispute start date
Whether June 2008 letter constituted admission the contract was in force and modified terms Letter and Edwards’ signed acknowledgement confirm contract remained in force and modifications were limited to rate/rig E & Pco: Letter merely discussed NorAm mitigating damages and renting rig; did not fix start date or admission of liability Court: Letter and signed acknowledgment reasonably confirm contract in full force and modifications; supports damages award

Key Cases Cited

  • Sun Exploration & Prod. Co. v. Benton, 728 S.W.2d 85 (Tex. 1987) (condition precedent and waiver principles)
  • Garza v. Southland Corp., 836 S.W.2d 214 (Tex. App.—Houston [14th Dist.] 1992) (party may waive a condition precedent)
  • Wes-Tex Tank Rental Inc. v. Pioneer Natural Res., 327 S.W.3d 316 (Tex. App.—Eastland 2010) (letter agreements can modify contracts)
  • BACM 2001-1 San Felipe Rd. v. Trafalgar Holdings I, 218 S.W.3d 137 (Tex. App.—Houston [14th Dist.] 2007) (letter modifications alter only referenced terms)
  • Wagner & Brown v. E.W. Moran Drilling Co., 702 S.W.2d 760 (Tex. App.—Fort Worth 1986) (validity of daywork contracts — payment due for availability even if no work performed)
Read the full case

Case Details

Case Name: Noram Drilling Co. v. E & Pco International, LLC
Court Name: Louisiana Court of Appeal
Date Published: Sep 30, 2015
Citations: 178 So. 3d 1061; 2015 WL 5714571; 2015 La. App. LEXIS 1906; No. 50,052-CA
Docket Number: No. 50,052-CA
Court Abbreviation: La. Ct. App.
Log In
    Noram Drilling Co. v. E & Pco International, LLC, 178 So. 3d 1061