History
  • No items yet
midpage
New York v. U.S. Nuclear Regulatory Commission
423 U.S. App. D.C. 1
| D.C. Cir. | 2016
Read the full case

Background

  • The NRC promulgated a Continued Storage Rule and a Generic Environmental Impact Statement (GEIS) addressing environmental impacts of continued on-site storage of spent nuclear fuel after reactor licensed life; this followed this Court’s vacatur of the NRC’s prior Waste Confidence Decision in New York I.
  • Petitioners (several states, a Native American community, and environmental groups) challenged the Rule and GEIS under NEPA, alleging failures to consider alternatives, mitigation, and accurate impacts/assumptions.
  • The NRC contended the Rule is a rulemaking that codifies generic environmental determinations to be applied in future site-specific licensing; the GEIS is intended as a generic analysis, with site-specific issues addressed in licensing proceedings or via waiver petitions.
  • Key contested topics included: whether the Rule required full site-specific EIS treatment of licensing alternatives and mitigation; whether the GEIS used conservative/bounding assumptions (population, pool fires/leaks, seismic risks); probability of failing to site a permanent repository; cumulative impacts; short-term high-volume pool leaks; and several long-term storage assumptions (60-year pool removal, 100-year dry cask replacement, perpetual institutional controls).
  • The D.C. Circuit reviewed whether the NRC’s GEIS and Rule complied with NEPA and whether the NRC’s technical assumptions were arbitrary or capricious under the Administrative Procedure Act.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Rule is a licensing action requiring site‑specific alternatives/mitigation in the GEIS Rule effectively decides licensing; so GEIS must include site-specific alternatives and mitigation Rule is a generic codification of environmental determinations, not a licensing action; site-specific alternatives/mitigation are addressed in licensing NRC correct: Rule is a major federal action but not a licensing action; GEIS suffices and site-specific review can address alternatives/mitigation
Whether GEIS failed to use conservative/bounding assumptions for common risks (population, seismic, pool fires/leaks) GEIS relied on limited sites/data and non‑bounding assumptions, understating impacts GEIS analyzed risks that are essentially common to sites, explained variance and limitations, and was thorough and comprehensive GEIS met NEPA’s "thorough and comprehensive" rule‑of‑reason; generic analysis appropriate for common risks
Whether NRC failed to quantify probability of failing to site a permanent repository and assess consequences NRC should quantify probability of repository failure and its impacts NRC need only quantify to the fullest extent practicable and may discuss qualitative factors when quantitative data lack NRC’s qualitative treatment of repository‑siting failure and its consequences satisfied NEPA requirements
Whether GEIS ignored cumulative impacts, short‑term high‑volume leaks, and whether waiver process is illusory GEIS segmented impacts, downplayed leaks; waiver shifts NEPA burden and is inadequate GEIS discussed cumulative impacts across reactor lifetime, analyzed leaks, and NRC provides waiver (§2.335) plus site licensing to raise site issues Court found GEIS adequately addressed cumulative impacts and leaks; waiver/admin avenues are adequate and reviewable in site proceedings
Whether key long‑term assumptions (60‑year pool removal; 100‑year dry cask replacement; perpetual institutional controls) are unreasonable Assumptions are speculative and underestimate risk Assumptions are supported by regulation, operational experience, cost analysis, and are reasonable predictive judgments Assumptions are not arbitrary or capricious; NRC’s predictive judgments are entitled to deference

Key Cases Cited

  • New York v. NRC, 681 F.3d 471 (D.C. Cir. 2012) (vacating NRC’s prior Waste Confidence Decision and Temporary Storage Rule)
  • Minnesota v. NRC, 602 F.2d 412 (D.C. Cir. 1979) (early remand of NRC’s on-site storage expansion decision)
  • In re Aiken County, 645 F.3d 428 (D.C. Cir. 2011) (DOE withdrawal of Yucca Mountain application context)
  • Blue Ridge Environmental Defense League v. NRC, 716 F.3d 183 (D.C. Cir. 2013) (deference to NRC technical judgments)
  • Motor Vehicle Manufacturers Ass'n v. State Farm Mut. Auto. Ins., 463 U.S. 29 (1983) (arbitrary and capricious standard)
  • Theodore Roosevelt Conservation Partnership v. Salazar, 661 F.3d 66 (D.C. Cir. 2011) (rule‑of‑reason in NEPA alternatives analysis)
  • Theodore Roosevelt Conservation Partnership v. Salazar, 616 F.3d 497 (D.C. Cir. 2010) (mitigation discussion not mandating implementation)
  • Kleppe v. Sierra Club, 427 U.S. 390 (1976) (cumulative impact requirement purpose)
  • Limerick Ecology Action, Inc. v. NRC, 869 F.2d 719 (3d Cir. 1989) (discussed on generic vs. site‑specific analysis)
  • New York v. EPA, 413 F.3d 3 (D.C. Cir. 2005) (deference to agency predictive judgments)
  • Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (agency technical judgments and petitioner substitution of analysis)
  • Public Utilities Commission of California v. FERC, 900 F.2d 269 (D.C. Cir. 1990) (permitting deferral of mitigation specifics to later stages)
  • Massachusetts v. NRC, 924 F.2d 311 (D.C. Cir. 1991) (site‑specific licensing challenges to NRC decisions)
  • York Committee for a Safe Environment v. NRC, 527 F.2d 812 (D.C. Cir. 1975) (review of final NRC licensing decision)
Read the full case

Case Details

Case Name: New York v. U.S. Nuclear Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jun 3, 2016
Citation: 423 U.S. App. D.C. 1
Docket Number: 14-1210; Consolidated with 14-1212, 14-1216, 14-1217
Court Abbreviation: D.C. Cir.