History
  • No items yet
midpage
New York-Connecticut Development Corp. v. Blinds-To-Go
159 A.3d 892
N.J. Super. Ct. App. Div.
2017
Read the full case

Background

  • NYCT was general contractor for BTG's headquarters under a written "GC Contract Cost Plus Fee with GMP" setting a guaranteed maximum price and completion date; parties agreed change orders procedure and submitted multiple change orders increasing the price.
  • Project was not completed by the contract date; CO issued March 16, 2012; NYCT stopped work before finishing punch list after a requisition dispute and later submitted a final requisition with over $1,000,000 in unapproved change orders.
  • NYCT sued for breach of contract and alternatively quantum meruit; BTG counterclaimed for NYCT's failure (including alleged failure to deliver LEED certification) but sought no monetary damages except as an offset/credit.
  • At trial both parties initially agreed a contract existed; the court nevertheless instructed the jury to decide whether a contract existed and to consider quantum meruit if there was no enforceable contract or if NYCT failed to perform.
  • The jury found a binding contract existed but that NYCT did not perform its obligations, yet awarded NYCT $791,046 under question 11 (quantum meruit).
  • Appellate court reversed and remanded for a new trial, holding that once a contract governs the subject matter, recovery under quantum meruit is precluded and the jury instructions/verdict sheet were legally erroneous and misleading.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether NYCT could recover under quantum meruit when an express contract governed the same subject matter NYCT argued it could plead alternative theories and, if the jury found no meeting of the minds or no enforceable contract/ performance, recover reasonable value BTG argued that an existing express contract on the identical subject bars quasi-contractual recovery Court held that an express contract excluding quantum meruit; once jury found a contract, quantum meruit relief was unavailable and instructions permitting it were erroneous
Whether the trial court erred in instructing jury to consider quantum meruit after finding a contract NYCT relied on right to plead inconsistent theories and requested alternative instruction BTG objected that permitting jury to award quantum meruit despite finding a contract misstates the law Court held the charge and verdict sheet misstated law; jury was improperly guided to consider quantum meruit after finding a contract
Whether defective jury instructions and verdict sheet were harmless error NYCT implicitly argued instructions allowed reasonable alternative findings BTG argued the flawed roadmap likely caused juror confusion and reversible error Court held erroneous instructions are not harmless here and reversed and remanded for new trial
Whether defendant's counterclaim/offset was properly presented to jury given verdict sheet/confusing instructions BTG contended counterclaim evidence entitled it to credit/offset against recovery NYCT maintained issues were resolved by contract questions as presented Court held the flawed verdict sheet prevented proper consideration of counterclaim; jury roadmap must be corrected on remand

Key Cases Cited

  • St. Barnabas Med. Ctr. v. Cnty. of Essex, 111 N.J. 67 (N.J. 1988) (describing quantum meruit as equitable, imposed to avoid unjust enrichment)
  • Weichert Co. Realtors v. Ryan, 128 N.J. 427 (N.J. 1992) (quantum meruit recovery available when one confers benefit and denial would be unjust)
  • Kas Oriental Rugs v. Ellman, 394 N.J. Super. 278 (App. Div. 2007) (existence of express contract excludes relief on same subject via quantum meruit)
  • E. Paralyzed Veterans Assoc. v. City of Camden, 111 N.J. 389 (N.J. 1988) (an implied contract cannot exist when an express contract governs identical subject)
  • Morton v. 4 Orchard Land Trust, 180 N.J. 118 (N.J. 2004) (meeting of the minds for contract formation shown by written offer and unconditional acceptance)
  • Das v. Thani, 171 N.J. 518 (N.J. 2002) (trial court must give accurate, controlling legal principles; charge is a jury roadmap)
  • State v. Afanador, 151 N.J. 41 (N.J. 1997) (erroneous jury instructions are ordinarily reversible error)
Read the full case

Case Details

Case Name: New York-Connecticut Development Corp. v. Blinds-To-Go
Court Name: New Jersey Superior Court Appellate Division
Date Published: Apr 10, 2017
Citation: 159 A.3d 892
Docket Number: A-5660-14T4
Court Abbreviation: N.J. Super. Ct. App. Div.