History
  • No items yet
midpage
NEST AND TOTAH VENTURE, LLC v. Deutsch
31 A.3d 1211
D.C.
2011
Read the full case

Background

  • NTV owns a DC condo building; Unit 800 was sold to WCD with a Seller Build Option for build-out.
  • WCD selected Valentine as general contractor; Valentine subcontracted to Kfoury, with NTV as Designated Contractor.
  • Build-Out Plans and timelines defined substantial completion and a closing date; dispute over whether completion occurred by February 1, 2007.
  • Escrow of $56,907 was created pending dispute over delay damages and closing.
  • WCD sued for breach; NTV counterclaimed for delay damages and 5% Build-Out Costs fees; trial court ruled for WCD on breach and fees but disputed the 5% fee and escrow handling.
  • Appellate court affirmed breach and construction coordination fee rulings, remanding only the attorneys’ fees issue to award total $100,000 in fees (including $56,907 previously subtracted from the cap) without prejudgment interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Substantial completion standard under contract NTV: Build-Out Work limited to Kfoury work WCD: Build-Out Work includes all Unit work, regardless of party Unit not substantially complete by Feb 1, 2007; closing premature
Whether Kfoury vs non-Kfoury work controls completion NTV: non-Kfoury work excluded from Build-Out Work WCD: Build-Out Work covers entire Unit No, broad Build-Out Work interpretation governs; completion requires all Build-Out Work
Construction coordination fee scope NTV: fees applied to all Build-Out Costs WCD: most costs excluded per prior agreement 5% fee due on $31,082; excluded items properly identified
Attorneys’ fees and escrow impact NTV: cap does not apply to fees, escrow counts WCD: cap applies; escrow funds offset fees Escrow funds not to be counted toward cap; remand to award total $100,000 in fees without prejudgment interest

Key Cases Cited

  • Jemison v. National Baptist Convention, USA, Inc., 720 A.2d 275 (D.C.1998) (review of trial court factual findings in a bench trial)
  • Unfoldment, Inc. v. District of Columbia Contract Appeals Bd., 909 A.2d 204 (D.C.2006) (contract interpretation using reasonable person standard)
  • Debnam v. Crane Co., 976 A.2d 193 (D.C.2009) (contract interpretation; extrinsic evidence for surrounding circumstances)
  • Akassy v. William Penn Apartments Ltd. P’ship, 891 A.2d 291 (D.C.2006) (reasonable-person standard; contract construction context)
  • 1010 Potomac Assocs. v. Grocery Mfrs. of Am., Inc., 485 A.2d 199 (D.C.1984) (surrounding circumstances in contract interpretation)
Read the full case

Case Details

Case Name: NEST AND TOTAH VENTURE, LLC v. Deutsch
Court Name: District of Columbia Court of Appeals
Date Published: Dec 1, 2011
Citation: 31 A.3d 1211
Docket Number: 09-CV-1149, 10-CV-261
Court Abbreviation: D.C.