236 F. Supp. 3d 1198
E.D. Cal.2017Background
- Plaintiffs (NRDC-led coalition) challenge Reclamation and FWS/NMFS decisions renewing and implementing long-term Central Valley water contracts (SRS and DMC) based on allegedly inadequate ESA Section 7 consultation, adding claims in the Fourth Supplemental Complaint (4SC).
- The 2004–05 FWS BiOps addressing delta smelt were later invalidated; FWS issued a 2008 BiOp finding jeopardy and Reclamation sought re-consultation; Reclamation obtained a 2015 letter of concurrence (LOC) asserting the 2008 BiOp addressed contract effects.
- Plaintiffs’ new claims: (Fourth) FWS failed to adequately re-consult re: delta smelt; (Fifth) Reclamation failed to reinitiate consultation with NMFS for winter- and spring-run Chinook based on new information; (Sixth) Reclamation and SRS Contractors unlawfully ‘took’ Chinook in 2014–2015 by depleting Shasta cold-water storage.
- Court stayed case for re-consultation, then allowed 4SC; motions to dismiss followed by supplemental briefing and the Court’s October 20, 2016 order narrowing issues and seeking briefing on whether contract terms leave Reclamation discretion to trigger re-initiation.
- The Court applies EPIC/Houston precedent to require that, for re-initiation based on executed contracts, plaintiffs must plausibly allege contractual or legal authority that leaves the agency discretion to modify contract terms (not just discretion in implementation).
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Reclamation retained sufficient discretionary involvement/control under SRS contracts to require re-initiation of consultation with NMFS (Fifth Claim). | Plaintiffs: contract provisions and agency practice leave Reclamation discretion over implementation (schedules, rates, transfers, forecasting) that could mitigate salmon harm, triggering §402.16(b). | Defs: EPIC/Houston require discretionary authority to modify executed contracts; SRS terms generally fix quantities/allocations and constrain meaningful unilateral modification. | Dismissed: Plaintiffs failed to plausibly allege contract-based discretion to materially revise executed contracts; Fifth Claim dismissed. |
| Whether SRS Contractors plausibly causally contributed to Section 9 take for 2014–2015 salmon deaths (Sixth Claim vs. contractors). | Plaintiffs: Contractors’ diversions were the physical mechanism that, but-for, led Reclamation to release water and deplete cold-water pool, causing lethal temperatures. | SRS Contractors: pleadings lack particularized factual allegations tying contractor acts to take. | Denied as to contractors: Court found plausible but-for causation from contractors’ diversions; claim proceeds against contractors. |
| Whether the 2009 NMFS OCAP BiOp Incidental Take Statement (ITS) shields Federal Defendants from Section 9 liability for the alleged takes. | Plaintiffs: ITS did not and could not cover non-discretionary deliveries to SRS contractors; ITS itself recognizes limits and excludes nondiscretionary deliveries. | Federal Defendants: the ITS covered overall OCAP impacts, so take is covered if ITS terms complied with. | Partially denied: Court concludes ITS does not plainly cover non-discretionary SRS deliveries; ITS unlikely to immunize Reclamation for non-discretionary contract-driven takes. |
| Whether Federal Defendants can be the proximate cause of Section 9 take for actions they are legally required to perform (non-discretionary). | Plaintiffs: agency liability can attach where agency conduct (including some discretionary implementation) proximately causes take. | Federal Defendants: Public Citizen / proximate-cause principles bar liability when agency lacks statutory ability to prevent the effect (i.e., actions are nondiscretionary). | Mixed: Court holds an agency implementing a legally mandated, non-discretionary contract term cannot be the proximate cause of Section 9 take; but Federal Defendants remain liable where they retain some control (narrowly allowed: where Reclamation may require GCID to divert up to 20,315 AF from Stony Creek and where approval of transfers proximately caused take). |
Key Cases Cited
- Nat. Res. Def. Council v. Jewell, 749 F.3d 776 (9th Cir. 2014) (agency retains “some discretion” at renewal stage triggering §7 consultation requirement)
- Envtl. Prot. Info. Ctr. v. Simpson Timber Co., 255 F.3d 1073 (9th Cir. 2001) (to require re-initiation, plaintiff must allege agency retained discretionary involvement/control sufficient to modify permit/contract terms to benefit other species)
- Nat’l Ass’n of Home Builders v. Defenders of Wildlife, 551 U.S. 644 (2007) (Section 7 applies only to actions with discretionary federal involvement or control)
- U.S. Dep’t of Transp. v. Public Citizen, 541 U.S. 752 (2004) (proximate-cause analysis limits agency responsibility where it lacks statutory ability to avoid the effect)
- Nat. Res. Def. Council v. Houston, 146 F.3d 1118 (9th Cir. 1998) (agency discretion during contract negotiation can trigger consultation obligations)
- San Luis & Delta-Mendota Water Auth. v. Locke, 776 F.3d 971 (9th Cir. 2014) (OCAP BiOps may evaluate overall impacts without segregating discretionary and nondiscretionary actions)
- TVA v. Hill, 437 U.S. 153 (1978) (ESA’s broad purpose to prevent extinction and conserve ecosystems)
