Name Redacted
ASBCA No. 60652
| A.S.B.C.A. | Feb 7, 2017Background
- Government awarded a firm‑fixed‑price commercial cleaning contract (W91B4M‑09‑P‑7340) to appellant on Sept. 15, 2009; contract ultimately reduced to $617 by mod P00003 after no work was performed.
- Contracting Officer (CO) and COR notified appellant that work could not proceed because personnel were not present; appellant signed the modification.
- Government attempted multiple times (emails 2013–2014) to close out the contract and sought a release of claims; funds were de‑obligated Aug. 23, 2014.
- Appellant filed this ASBCA appeal on June 28, 2016, alleging it incurred DBA and $27,000 mobilization costs and that the KO/COR told it they would email directions to seek payment.
- Government moved to dismiss for lack of jurisdiction, arguing appellant never submitted a written claim to the CO and thus no CO final decision (or deemed denial) occurred.
- Appellant did not produce a written claim: its responses addressed different prior/different appeals and failed to show a written demand to the CO for the DBA/mobilization costs. The Board ordered production of a claim; appellant’s reply remained unresponsive.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Board has jurisdiction under the CDA because appellant submitted a claim to the CO seeking DBA and mobilization costs | Appellant contends it notified the KO and COR and awaited their email to process DBA and mobilization payment (i.e., they communicated their demand) | Government contends no written claim was submitted to the CO and no CO final decision exists, so the Board lacks CDA jurisdiction | Held: No. Appellant failed to show a written claim was submitted to the CO; jurisdiction lacking; appeal dismissed without prejudice |
Key Cases Cited
- Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586 (Fed. Cir. 1987) (claim must be written, submitted to CO, and give adequate notice of basis and amount)
