midpage
Projects
Sign in to see your projects.
794 F.Supp.3d 1093
E.D. Okla.
2025
Read the full case

Background

  • Morse Electric, Inc. (MEI) was hired by Stearns, Conrad and Schmidt, Consulting Engineers, Inc. (SCS) to perform electrical construction for the Pine Bend Renewable Natural Gas Production Facility in Minnesota.
  • The subcontract was a fixed price, lump sum contract with provisions for change orders, retainage, and a requirement that MEI perform the work diligently and continue work during disputes.
  • Project drawings were periodically updated via bulletins; MEI was responsible for requesting change orders if updates impacted costs/schedule.
  • Disputes arose over payment, scope changes, delays, and whether SCS or MEI breached their contractual obligations first; MEI walked off the job in February 2022, after submitting contested change orders and invoices.
  • SCS then hired PCL Industrial Services, Inc. to complete the remaining electrical work; SCS counterclaimed for breach of contract.
  • The court held a bench trial and ruled for SCS on all substantive claims, awarding it damages and attorney’s fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Breach of Contract by SCS SCS delayed, incorrectly handled change orders, failed to pay invoices, and hindered performance MEI walked off job, failed to follow dispute provisions, SCS fulfilled duties; any delays or payment withholdings were justified MEI first materially breached by abandoning the site; SCS performed under the contract
Right to Additional Payment (Change Orders) MEI entitled to increased payment due to changes in scope/bulletins not clouded properly MEI failed to timely request change orders for changes; MEI responsible for tracking and requesting adjustments SCS did not materially breach by denying late change orders or failing to cloud drawings; MEI's claim denied
Minnesota Prompt Payment Act Violation SCS failed to promptly pay for undisputed work after receiving owner payments Invoice and changes were disputed, payments not due prior to SCS receiving funds, and non-payment was not a breach SCS did not violate the MPPA; no payment was due for disputed invoices
Recovery of Damages by SCS SCS not entitled or unreasonably claimed excessive completion costs by hiring PCL on time & materials basis SCS reasonably hired PCL to finish abandoned work and calculated damages as contract allows SCS entitled to recover $698,674 in reasonable excess completion costs

Key Cases Cited

  • Nelson v. Am. Fam. Mut. Ins. Co., 899 F.3d 475 (8th Cir. 2018) (sets forth elements of breach of contract under Minnesota law)
  • Carlson Real Est. Co. v. Soltan, 549 N.W.2d 376 (Minn. Ct. App. 1996) (prior material breach precludes recovery for subsequent breaches)
  • Blaine Econ. Dev. Auth. v. Royal Elec. Co., 520 N.W.2d 473 (Minn. Ct. App. 1994) (damages for contract default include reasonable cost of completion)
  • Christenson v. Milde, 402 N.W.2d 610 (Minn. Ct. App. 1987) (damages should place non-breaching party as if contract performed)
  • Zobel & Dahl Constr. v. Crotty, 356 N.W.2d 42 (Minn. 1984) (contract performance excused if hindered by other party)
  • Grant v. Munch, 55 N.W. 902 (Minn. 1893) (time is of the essence clause interpreted strictly when expressly included)
Read the full case

Case Details

Case Name: Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc.
Court Name: District Court, E.D. Oklahoma
Date Published: Jul 23, 2025
Citations: 794 F.Supp.3d 1093; 6:22-cv-00091
Docket Number: 6:22-cv-00091
Court Abbreviation: E.D. Okla.
Log In
    Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc., 794 F.Supp.3d 1093