History
  • No items yet
midpage
Moore v. Goran, LLC
2017 MT 208
| Mont. | 2017
Read the full case

Background

  • Moore owned a gravel pit (Moore Pit) and contracted with Goran (a contractor on an MDT project) to sell crushed aggregate; Goran’s form contract was used.
  • Contract specified material sold by the ton and included the term “F.O.B. Moore Pit”; parties routinely weighed loads on Moore Pit scales and Goran was invoiced weekly based on those scale weights.
  • After removing material, Goran paid most invoices but refused to pay final invoices; Moore sued for breach of contract, Prompt Payment Act violation, and unjust enrichment; Goran counterclaimed.
  • Moore moved for summary judgment arguing the contract unambiguously required payment by ton as measured at the Moore Pit scales; the district court granted summary judgment for Moore, awarding $66,269.95 plus fees.
  • On appeal Goran argued a factual dispute existed over quantity removed and that contract delivery meant delivery to the Red Lodge Tied Projects (MDT measurements by volume), not at the Moore Pit.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Proper measurement and basis for payment Moore: contract sells material by the ton; payment based on Moore Pit scale weights. Goran: quantity should be measured by MDT volume measurements at the project site; contract doesn’t specify measurement point. Held: Contract required sale by weight; Moore Pit scales were the contractual measurement point.
Point of delivery / transfer of title and risk Moore: "F.O.B. Moore Pit" makes Moore’s delivery at the pit the point of delivery; title/risk pass at pickup. Goran: "project" means the Red Lodge Tied Projects and delivery occurs at the project site. Held: "F.O.B. Moore Pit" is a shipment contract; delivery, title, and risk passed at Moore Pit.
Sufficiency of evidence to create genuine factual dispute Moore: Goran produced no admissible evidence disputing the tonnage measured at Moore Pit. Goran: Affidavit and MDT documents show different quantities (volume), creating dispute. Held: Goran failed to authenticate MDT documents and Cusick lacked personal knowledge; no genuine issue of material fact.
Appropriateness of summary judgment Moore: undisputed contract terms and admissible evidence support summary judgment. Goran: factual disputes preclude summary judgment. Held: Summary judgment affirmed for Moore; Goran did not present substantial admissible evidence of a material dispute.

Key Cases Cited

  • Ophus v. Fritz, 301 Mont. 447, 11 P.3d 1192 (Mont. 2000) (interpretation of written contract is question of law)
  • Mary J. Baker Revocable Trust v. Cenex Harvest States Coops., Inc., 338 Mont. 41, 164 P.3d 851 (Mont. 2007) (contract interpretation principles)
  • Pilgeram v. GreenPoint Mortgage Funding, Inc., 373 Mont. 1, 313 P.3d 839 (Mont. 2013) (standard of review for summary judgment)
  • Elk v. Healthy Mothers, Healthy Babies, Inc., 316 Mont. 320, 73 P.3d 795 (Mont. 2003) (evidence required to create genuine factual dispute on summary judgment)
  • Alfson v. Allstate Property and Casualty Ins. Co., 372 Mont. 363, 313 P.3d 107 (Mont. 2013) (unauthenticated documents inadmissible on summary judgment)
  • Litecubes, LLC v. Northern Light Prods., 523 F.3d 1353 (Fed. Cir. 2008) (F.O.B. term as term of art under UCC)
Read the full case

Case Details

Case Name: Moore v. Goran, LLC
Court Name: Montana Supreme Court
Date Published: Aug 22, 2017
Citation: 2017 MT 208
Docket Number: DA 17-0032
Court Abbreviation: Mont.