History
  • No items yet
midpage
355 P.3d 1222
Wyo.
2015
Read the full case

Background

  • Farmers Canal Permit No. 854 (filed 1894) originally covered Tract 109 (161.73 acres) but no certificate of appropriation was ever issued for that tract under Permit 854.
  • In 1916 Levi Johnson (predecessor to Mohr) applied for and received Permit No. 3712E (Perkins Ditch Enlargement) to irrigate Tract 109; he executed an affidavit stating Farmers Canal water had not been used on Tract 109, asking cancellation of Permit 854 as to that tract.
  • Johnson completed works and proved appropriation; the Board issued a certificate for Tract 109 under the Perkins Ditch Enlargement (priority 1916; perfected by certificate in 1922). Since at least 1922 Tract 109 has been irrigated under Permit 3712E, though conveyance has sometimes been via Farmers Canal.
  • During Phase III of the Big Horn River general adjudication, the Board/Administrator recommended eliminating unadjudicated acreage from Permit 854, including Tract 109, because Tract 109 was adjudicated under Permit 3712E.
  • The Special Master and district court recommended and adopted elimination of Tract 109 from Permit 854; Mohr (current owner) appealed, arguing Johnson’s affidavit did not relinquish the Farmers Canal right and asserting procedural errors; the Supreme Court affirmed.

Issues

Issue Plaintiff's Argument (Mohr) Defendant's Argument (State/Board) Held
Whether Mohr is bound by predecessor’s acts/adjudication Predecessor’s affidavit and actions did not legally eliminate Farmers Canal right; Mohr not bound Johnson’s affidavit and subsequent perfecting of Perkins Ditch showed waiver/relinquishment; property bound by predecessor Held: Mohr is bound; predecessor waived Farmers Canal right by affidavit and perfecting Permit 3712E; Tract 109 eliminated from Permit 854
Whether Farmers Canal Permit was perfected for Tract 109 before 1916 Mohr argued uncertainty about pre-1916 use supports retaining Permit 854 right State: no proof of beneficial use under Permit 854 for Tract 109; Perkins Ditch was perfected instead Held: No clear evidence of pre-1916 beneficial use under Permit 854; Permit 854 remained inchoate for Tract 109
Whether affidavit effected abandonment vs. waiver Mohr suggested affidavit insufficient to constitute abandonment/forfeiture under statutory procedures State argued affidavit manifested intent to relinquish and, with subsequent perfection of 3712E, operated as waiver Held: Court treats Johnson’s affidavit plus actions as an effective waiver; statutory formal abandonment not required where waiver is clear and right was perfected under another permit
Whether Mohr received fair procedural process under W.R.C.P. Mohr alleged multiple procedural violations by district court State/district court: procedures followed; Mohr offered no cogent argument or authority showing harm Held: Procedural claims rejected for lack of cogent argument and failure to show prejudice; court’s process adequate

Key Cases Cited

  • In re General Adjudication of All Rights to Use Water in Big Horn River System, 803 P.2d 61 (Wyo. 1990) (describes phased general adjudication structure)
  • In re General Adjudication of All Rights to Use Water in Big Horn River System, 85 P.3d 981 (Wyo. 2004) (explains three-step water-permitting/appropriation process)
  • Green River Dev. Co. v. FMC Corp., 660 P.2d 339 (Wyo. 1983) (distinguishes inchoate vs. perfected water rights; importance of certificate of appropriation)
  • Jensen v. Fremont Motors Cody, Inc., 58 P.3d 322 (Wyo. 2002) (defines waiver elements: existing right, knowledge, and intent to relinquish)
  • Campbell v. Wyoming Development Co., 100 P.2d 124 (Wyo. 1940) (successors in interest take no better position than predecessors)
Read the full case

Case Details

Case Name: Mohr v. State
Court Name: Wyoming Supreme Court
Date Published: Aug 13, 2015
Citations: 355 P.3d 1222; 2015 WY 104; 2015 Wyo. LEXIS 119; 2015 WL 4761438; No. S-15-0008
Docket Number: No. S-15-0008
Court Abbreviation: Wyo.
Log In
    Mohr v. State, 355 P.3d 1222