History
  • No items yet
midpage
MKP Enterprises, Inc. v. Underground Storage Tank Indemnification Board
2012 Pa. Commw. LEXIS 62
| Pa. Commw. Ct. | 2012
Read the full case

Background

  • EPI operates three underground storage tanks in Erie; during excavation on November 6, 2007, contamination around spill buckets was observed and the tanks were removed and replaced the next day.
  • The Underground Storage Tank Indemnification Fund denied EPI’s claim (April 2008) because EPI allegedly failed to notify the Fund within 60 days after confirmation of the release.
  • EPI challenged the denial; the Presiding Officer found EPI ineligible for coverage due to untimely notification, and the Board adopted the PO’s report.
  • DEP received notice of the release via a NORR and DEP faxed a copy to the Fund; the NORR bore signatures indicating a confirmed release in November 2007.
  • Section 977.34 requires notification to the Fund within 60 days after confirmation of a release under DEP regulations; the Board held the 60-day window began in November 2007.
  • EPI petitioned for review, asserting multiple regulatory, preemption, and procedural issues, including nunc pro tunc relief and an application of Harrisburg Jet Center precedent.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was EPI’s notice to the Fund timely under 977.34? EPI argued DEP/DEP-notified form satisfied notice to the Fund within 60 days. Board held only a participant may notify the Fund; notice must be timely by the participant. Untimely; 60 days from November 2007 denial of release ran before April 2008 filing.
Does DEP’s NORR/Notification Form satisfy the Fund’s notice requirement? DEP’s transmission to the Fund could constitute notice to the Fund. Notice to DEP alone does not fulfill 977.34’s requirement that a participant notify the Fund. No; notice to DEP via NORR does not satisfy the Fund’s separate notice requirement.
Does Harrisburg Jet Center impose an improper constructive-knowledge standard for accrual date? Harrisburg Jet Center should not apply; it used a constructive knowledge approach. Harrisburg Jet Center aligns with a standard that factual knowledge can trigger accrual. Board’s approach, aligning with Harrisburg Jet Center, is not improper; actual knowledge supported accrual date.
Should nunc pro tunc relief have been granted? Delay was excusable; circumstances justified nunc pro tunc relief. No breakdown in process; regulation not confusing; no extraordinary circumstances shown. Denied; no extraordinary circumstances; rule not confusing; no nunc pro tunc relief.

Key Cases Cited

  • Rohde v. Unemployment Comp. Bd. of Rev., 28 A.3d 237 (Pa. Cmwlth. 2011) (substantial evidence standard in review)
  • Taylor v. Unemployment Compensation Bd. of Rev., 474 Pa. 351 (1977) (substantial evidence review framework)
  • Penflex, Inc. v. Bryson, 506 Pa. 274 (Pa. 1984) (standard for binding findings on review)
  • Fid. & Guar. Ins. Co. v. Bureau of Workers’ Comp. (Cmty. Med. Ctr.), 13 A.3d 534 (Pa. Cmwlth. 2010) (reasonableness of regulatory time limits; statutory delegation)
  • Gibson v. Unemployment Compensation Bd. of Rev., 682 A.2d 422 (Pa. Cmwlth. 1996) (agency position changes require explanation)
  • Dwyer v. Commonwealth, 849 A.2d 1274 (Pa. Cmwlth. 2004) (nunc pro tunc review not available for non-confusing regulations)
Read the full case

Case Details

Case Name: MKP Enterprises, Inc. v. Underground Storage Tank Indemnification Board
Court Name: Commonwealth Court of Pennsylvania
Date Published: Feb 9, 2012
Citation: 2012 Pa. Commw. LEXIS 62
Court Abbreviation: Pa. Commw. Ct.