History
  • No items yet
midpage
MISO Transmission Owners v. Federal Energy Regulatory Commission
860 F.3d 837
| 6th Cir. | 2017
Read the full case

Background

  • MISO is a regional transmission organization that approves transmission expansion projects and allocates costs to member utilities under a filed Tariff.
  • American Transmission Systems (ATSI) and Duke Energy’s Ohio/Kentucky utilities notified MISO of withdrawal (2009–2010) and had earliest possible exit dates at the end of the year following notice.
  • MISO created a new, higher-cost project category—Multi-Value Projects (MVPs)—and approved a portfolio of MVPs in December 2011 shortly before Duke’s scheduled departure.
  • MISO added Schedule 39 and Attachment MM, which the FERC approved prospectively, to charge ex-members for MVP costs using an MVP Usage Charge based on annual energy withdrawals.
  • FERC later held Schedule 39 could not be applied retroactively to charge Duke and ATSI for MVPs approved before their departures; other MISO Transmission Owners appealed that FERC interpretation to the Sixth Circuit.

Issues

Issue Petitioners' Argument Respondent's Argument Held
Venue: Is Sixth Circuit an appropriate forum Petitioners filed in Sixth Circuit (ties to Ohio/KY utilities) — venue proper FERC questioned venue but did not move to transfer Venue not objected to; Sixth Circuit retains case; no transfer warranted
Standard of review for FERC tariff interpretation Petitioners urged less deference to FERC FERC argued deference where based on technical expertise Court reviews legal questions afresh but would affirm under either fresh or deferential review
Whether pre-Schedule 39 Tariff made withdrawing members liable for MVP costs approved before exit Petitioners: costs allocated at approval; withdrawing members (present at approval) incurred obligations FERC/Intervenors: MVPs allocate "annual revenue requirements" by usage; no up-front liability before construction/usage Held: Tariff allocates MVP costs year-to-year via Usage Charge; withdrawing utilities did not incur pre-departure obligations and are not retroactively liable
Whether FERC departed from prior orders or failed to reason adequately Petitioners: FERC departed from earlier reasoning and lacked adequate explanation FERC: prior orders did not decide timing of MVP allocation; its reasoning is supported by Tariff text Held: No unexplained departure; FERC’s explanation was sufficient and not arbitrary or capricious

Key Cases Cited

  • Ill. Commerce Comm’n v. FERC, 721 F.3d 764 (7th Cir. 2013) (describing MISO and its region)
  • Pub. Serv. Comm’n of Wis. v. FERC, 545 F.3d 1058 (D.C. Cir. 2008) (background on FERC approval of MISO Tariff changes)
  • Ark. La. Gas Co. v. Hall, 453 U.S. 571 (1981) (filed-rate doctrine and prohibition on retroactive ratemaking)
  • Panhandle E. Pipe Line Co. v. Fed. Power Comm’n, 324 U.S. 635 (1945) (venue rules under federal utility statutes)
  • FERC v. Elec. Power Supply Ass’n, 136 S. Ct. 760 (2016) (standard for reviewing FERC orders)
  • Cincinnati Gas & Elec. Co. v. FERC, 724 F.2d 550 (6th Cir. 1984) (Sixth Circuit’s approach to deference on tariff interpretation)
  • Encino Motorcars, LLC v. Navarro, 136 S. Ct. 2117 (2016) (agency explanation must allow the court to discern its path)
Read the full case

Case Details

Case Name: MISO Transmission Owners v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the Sixth Circuit
Date Published: Jun 21, 2017
Citation: 860 F.3d 837
Docket Number: 16-3791
Court Abbreviation: 6th Cir.