Mira Mar Development Corporation v. City of Coppell, Texas
421 S.W.3d 74
Tex. App.2013Background
- Mira Mar purchased ~18.5 acres to develop a 29‑lot subdivision (Alexander Court) and later sold lots to David Weekley Homes. Disputes arose with City of Coppell over development conditions, delays, design changes, and fees.
- Mira Mar sought compensation via a city‑council hearing under Tex. Loc. Gov’t Code § 212.904; the council’s first hearing procedures were held inadequate and a second, court‑reported hearing was conducted.
- After the second hearing the City awarded Mira Mar roughly $31,496 (including some construction costs) and $1,800 attorney’s fees; the trial court later added $8,785 for land under an offsite sidewalk and vacated the attorney’s fee award.
- Parties filed competing summary‑judgment motions; the trial court granted the City’s motion, denied Mira Mar’s, and entered judgment awarding Mira Mar $40,280.84 and denying attorney’s fees.
- On appeal the court reviewed which developer requirements were compensable exactions (focusing on the Nollan/Dolan/Stafford rough‑proportionality test), which items City proved were roughly proportional, and whether § 212.904 procedures and remedies (including attorney’s fees and standard of review) were applied correctly.
Issues
| Issue | Plaintiff's Argument (Mira Mar) | Defendant's Argument (Coppell) | Held |
|---|---|---|---|
| Whether various permit conditions were compensable exactions under federal/state takings law | City conditioned approvals on payments/improvements; those are exactions requiring compensation unless roughly proportional | Many conditions were legitimate regulatory requirements or within engineer discretion and were roughly proportional | Court applied Nollan/Dolan/Stafford; split rulings by item — some were compensable, others not |
| Rolled curbs / street‑width requirement | City’s straight curb requirement increased lot costs and reduced sale price; claimed uncompensated exaction | City made individualized safety determination requiring wider streets with straight curbs; requirement tied to public safety | Requirement upheld as non‑compensable (rough proportionality and nexus established) |
| Offsite sidewalk (cost + land value) | Entitled to cost + value of land under sidewalk ($21,465) | City paid construction cost but not land value; contested amount | Court rendered judgment awarding full $21,465 (plaintiff prevailed on land value) |
| Storm‑drain extension, riprap, piers | Required unnecessary extension to creek and extra works — compensable | City engineer asserted necessity to prevent erosion/flooding | Court reversed summary judgment for City on pipe extension/riprap/piers (insufficient evidence of nexus/proportionality); remanded for further proceedings |
| Tree mitigation ("retribution") fees | Fees ($34,500) were exactions not shown to be roughly proportional to development’s impact | City argued fees advance legitimate public forestry programs and are tied to removed tree inches | Court rendered judgment for Mira Mar: fees not shown to be roughly proportional; $34,500 awarded |
| Park and inspection fees; construction inspection fees | Fees were exactions and not shown roughly proportional | City asserted fees tied to per‑unit or inspection costs; offered only conclusory testimony | Court reversed on park fees and construction‑inspection fees (City failed to prove rough proportionality); remanded for fact issues on proportional amounts |
| Water/sewer impact fees and who pays | Mira Mar sought compensation for water/sewer fees passed to builder (reduced lot price) | City: water/sewer fees are paid at building permit by builder, not a conditioned exaction against Mira Mar | Court: water/sewer fees were not exactions against Mira Mar; trial court’s ruling not reviewable on that ground here |
| Whether trial court should have used trial de novo (and jury) under § 212.904 appeals | Mira Mar: appellate appeal under § 212.904 should be tried de novo in court and compensation issues (amount) are jury issues | City accepted court review but relied on substantial‑evidence review of council | Court: appeal from council on exactions should be trial de novo for mixed legal/constitutional questions; factual takings issues tried to judge but compensation amount (if any) is for jury; remanded to allow appropriate proceedings |
| Attorney’s fees under § 212.904 | Mira Mar argued it prevailed and is entitled to fees for the § 212.904 appeal(s) | City argued Mira Mar did not ‘‘prevail’’ sufficiently (recovery small vs. claimed) | Court reversed denial of fees in part and remanded fee determination to trial court consistent with new rulings (plaintiff recovered on several items and fee remand appropriate) |
Key Cases Cited
- Mayhew v. Town of Sunnyvale, 964 S.W.2d 922 (Tex. 1998) (distinguishes physical vs. regulatory takings and takings law principles)
- Dolan v. City of Tigard, 512 U.S. 374 (1994) (establishes essential‑nexus and rough‑proportionality tests for exactions)
- Nollan v. California Coastal Comm’n, 483 U.S. 825 (1987) (essential‑nexus requirement for imposed conditions)
- Town of Flower Mound v. Stafford Estates Ltd. P’ship, 135 S.W.3d 620 (Tex. 2004) (adopts/clarifies rough‑proportionality test in Texas)
- FM Props. Operating Co. v. City of Austin, 22 S.W.3d 868 (Tex. 2000) (standards for reviewing cross‑motions for summary judgment)
- Riner v. Neumann, 353 S.W.3d 312 (Tex. App.—Dallas 2011) (affidavit/conclusory testimony insufficient to support summary judgment)
- City of Houston v. Clear Creek Basin Auth., 589 S.W.2d 671 (Tex. 1979) (limits on affirming grounds not raised below)
- Gen. Servs. v. Little‑Tex Insulation Co., 39 S.W.3d 591 (Tex. 2001) (whether facts constitute a taking is question of law)
- Armstrong v. United States, 364 U.S. 40 (1960) (principle that public should bear public burdens fairly)
- Intercontinental Group P’ship v. KB Home Lone Star L.P., 295 S.W.3d 650 (Tex. 2009) (definition of prevailing party for fee awards)
