History
  • No items yet
midpage
Miller-Davis Co. v. Ahrens Construction, Inc.
495 Mich. 161
| Mich. | 2014
Read the full case

Background

  • Miller-Davis, the general contractor, sued Ahrens (subcontractor) and Merchants Bonding for breach of contract over a defective natatorium roof installation, with the subcontract incorporating plans, specifications, and an indemnity clause.
  • Ahrens installed the roof and, after a moisture problem (NMP) arose, the project architects found deficiencies; corrective work was undertaken and final payment occurred in February 2000.
  • In 2003, architects identified substantial nonconforming installation; Miller-Davis and YMCA entered into an Agreement for Corrective Work to address the issues, resolving claims without litigation.
  • Trial court awarded Miller-Davis damages for the corrective work; the Court of Appeals reversed in part, holding that § 600.5839(1) barred Miller-Davis’s contract claims and that the indemnity issue remained unresolved.
  • Supreme Court granted leave, held that indemnity clauses apply to the corrective-work breach, that Sherman Lake YMCA made a claim triggering indemnity, and that the indemnity claim accrues separately from the underlying breach; case remanded for judgment and potential attorney’s fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Do indemnity clauses apply here? Miller-Davis argues indemnity covers all damages from Ahrens’s breach. Ahrens contends indemnity should not apply absent a qualifying claim. Indemnity clauses apply to Miller-Davis’s corrective-work damages.
Is causation required to prove indemnity damages? Damages arise from Ahrens’s breach of the indemnity, not necessarily the NMP causation. Damages must be tied to the NMP causation. Damages are caused by Ahrens’s breach of indemnity; NMP causation is not required for indemnity damages.
Does the six-year statute of limitations bar the indemnity claim? Indemnity breach occurred within six years of accrual. The accrual date should align with the underlying breach. Not barred; indemnity accrual is distinct and occurred after the underlying breach.
When does accrual for the indemnity claim occur? Accrual could be tied to the initial breach. Accrual should occur when the indemnified loss is sustained or when indemnity is triggered. Accrual for indemnity occurs after Ahrens breaches the indemnity obligation, separate from the initial breach.
Should the case be remanded for judgment and attorney’s fees? If indemnity is viable, Miller-Davis seeks fees under the indemnity clause. Fees should be determined after resolving indemnity viability. Remand for judgment in Miller-Davis’s favor and for determination of attorney’s fees.

Key Cases Cited

  • Miller-Davis Co v Ahrens Constr, Inc (On Remand), 296 Mich App 56 (2012) (indemnity accrual and damages analysis on remand)
  • Miller-Davis Co v Ahrens Constr, Inc, 489 Mich 355 (2011) (forecloses a single accrual date for indemnity under MCL 600.5807(8) roofing dispute)
  • Grand Trunk W R, Inc v Auto Warehousing Co, 262 Mich App 345 (2004) (contract-law principles; accrual and damages analysis)
  • Ins Co of North America v Southeastern Electric Co Inc, 405 Mich 554 (1979) (indemnity and damages causation principles in Michigan)
  • Employers Mut Cas Co v Petroleum Equip, Inc, 190 Mich App 57 (1991) (causation and indemnity contract principles)
  • Smith Trust, 480 Mich 19 (2008) (contract interpretation and accrual concepts in Michigan)
Read the full case

Case Details

Case Name: Miller-Davis Co. v. Ahrens Construction, Inc.
Court Name: Michigan Supreme Court
Date Published: Apr 15, 2014
Citation: 495 Mich. 161
Docket Number: Docket 145052
Court Abbreviation: Mich.