History
  • No items yet
midpage
Miken Technologies, Inc. v. Traffic Law Headquarters, P.C.
2016 Mo. App. LEXIS 690
| Mo. Ct. App. | 2016
Read the full case

Background

  • TLH contracted with Miken on July 26, 2012 for a client-management application; agreed total price initially ~$12,800–$14,100 and Miken estimated up to 141 hours; TLH paid $7,500 upfront for database design.
  • Miken estimated the design phase would take 10–12 hours but billed 73 hours and took 10 months for design; after ~18 months Miken had billed 157 hours and about $15,700 total.
  • TLH terminated the contract on January 17, 2014, citing lack of timeline, phase/task dates, periodic updates, failure to produce/test/deploy a working database, and unreasonable delay.
  • Miken claimed the job was 90% complete (offering source code for $7,500) and sued for $7,500 in damages; TLH counterclaimed for return of the $7,500 upfront payment.
  • The trial court found Miken materially breached the contract, concluded TLH received nothing of value, and awarded TLH $7,500; the court denied Miken’s breach claim.

Issues

Issue Plaintiff's Argument (Miken) Defendant's Argument (TLH) Held
Whether Miken breached the contract by excessive delay/nonperformance Miken: ~90% of work complete; delay reasonable in part because TLH delayed feedback; no firm deadline in contract TLH: Delay (1.5 years) and failure to deliver a functioning product was a substantial/material breach Court: Miken materially breached; TLH entitled to return of $7,500 prepaid
Whether Miken may recover on quantum meruit for work performed Miken: Should be compensated for 157 hours/90% work under unjust enrichment/quantum meruit TLH: Recovery not pleaded; TLH seeks refund because it received no usable product Court: Quantum meruit claim not pleaded at trial; court will not consider unpleaded claim on appeal

Key Cases Cited

  • Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976) (standard of review for court-tried cases)
  • Hastings & Chivetta Architects v. Burch, 794 S.W.2d 294 (Mo.App.E.D.1990) (law implies a reasonable time to perform when no time fixed)
  • McCandlish v. Estate of Timberlake, 497 S.W.2d 191 (Mo.App.1973) (amount due when party has fully performed and nothing remains)
  • Fire Sprinklers, Inc. v. Icon Contracting, Inc., 279 S.W.3d 230 (Mo.App.E.D.2009) (non-breaching party may terminate for material breach and sue for total breach)
  • County Asphalt Paving Co., Inc. v. Mosley Const., Inc., 239 S.W.3d 704 (Mo.App.E.D.2007) (quantum meruit prevents unjust enrichment; recovery limited to reasonable value)
  • Browning-Ferris Indus. of St. Louis, Inc. v. Landmark Sys., Inc., 822 S.W.2d 569 (Mo.App.E.D.1992) (cannot recover on unpleaded cause of action)
Read the full case

Case Details

Case Name: Miken Technologies, Inc. v. Traffic Law Headquarters, P.C.
Court Name: Missouri Court of Appeals
Date Published: Jul 12, 2016
Citation: 2016 Mo. App. LEXIS 690
Docket Number: ED 103620
Court Abbreviation: Mo. Ct. App.