History
  • No items yet
midpage
Mid Am. Constr., L.L.C. v. Univ. of Akron
2019 Ohio 3863
Ohio Ct. App.
2019
Read the full case

Background

  • MAC contracted with the University of Akron (Dec. 2014) as general trades contractor for the Zook Hall Renovation Phase 2B; project was multi‑prime with CM Thomarios and architect Stantec.
  • Project suffered repeated delays; many RFIs went unanswered or CCDs were issued unsigned, and the CM’s schedule contained logic defects and poor coordination among primes.
  • University stopped paying MAC (~Sep. 2015), issued a 5‑day termination notice and then a Notice of Termination (Jan. 2016), claiming MAC was in default; Fidelity (MAC’s surety) executed a takeover agreement but the University withheld contract funds.
  • Fidelity appointed MAC to continue work under a takeover agreement; MAC self‑funded work, then demobilized May 27, 2016 due to continued nonpayment; project finally completed Aug. 16, 2016.
  • Court of Claims awarded MAC and Fidelity $2,258,700, finding the University breached the original and takeover agreements (termination was effectively for convenience and University failed to pay); this decision was affirmed on appeal.

Issues

Issue Plaintiff's Argument (MAC/Fidelity) Defendant's Argument (University) Held
Was termination for cause or for convenience? University lacked cause because delays were caused or contributed to by Stantec and Thomarios (unanswered RFIs, unsigned CCDs, schedule/coordination failures). MAC alone caused delays (83 days behind), failed to provide required recovery plan, so termination for cause was justified. Termination was for convenience; Court of Claims’ weighing of scheduling, RFI/CCD and CM failures supported finding University lacked cause.
Can MAC recover under takeover agreement via Fidelity’s assignment? Fidelity assigned its rights to MAC; MAC performed under takeover and was entitled to funds. Assignment or contract language (e.g., anti‑assignment clause) precludes MAC recovery; no consideration from Fidelity to MAC. Assignment was valid: MAC substantially performed and relieved Fidelity; University breached by withholding funds; MAC/Fidelity may recover.
Did the award improperly include payment for work not performed (contract alternatives) or overcompensate? Award reflects work performed, change orders, and deductions for alternatives; MAC did not claim payment for certain alternatives. Award equals full contract price less prior payments and thus must have paid for unperformed alternative work (G‑1, G‑5). Appellate court: University failed to show the award included payment for unperformed alternatives; damage amount was a factual finding not against manifest weight.
Is University entitled to setoff or liquidated (statutory) delay damages? University sought setoff for cost to complete and liquidated damages under contract. MAC argued University’s breaches (nonpayment, CM/A/E delays) excused MAC’s noncompletion and precluded liquidated damages. Court denied University setoff and liquidated damages: University materially breached and contributed to delays; liquidated damages not available where owner’s actions contributed to delay.

Key Cases Cited

  • Eastley v. Volkman, 132 Ohio St.3d 328 (Ohio 2012) (explains manifest‑weight standard of review for factual findings)
  • State v. Thompkins, 78 Ohio St.3d 380 (Ohio 1997) (on the meaning and application of weight of the evidence)
  • Travelers' Ins. Co. v. Gath, 118 Ohio St. 257 (Ohio 1928) (defines preponderance as greater weight of the evidence)
  • Arbino v. Johnson & Johnson, 116 Ohio St.3d 468 (Ohio 2007) (damages are a factfinder province)
  • In re Interstate Bakeries Corp., 751 F.3d 955 (8th Cir. 2014) (discusses relationship between substantial performance and material breach)
Read the full case

Case Details

Case Name: Mid Am. Constr., L.L.C. v. Univ. of Akron
Court Name: Ohio Court of Appeals
Date Published: Sep 24, 2019
Citation: 2019 Ohio 3863
Docket Number: 18AP-846
Court Abbreviation: Ohio Ct. App.