midpage
Projects
Sign in to see your projects.
2016 Ohio 3276
Ohio Ct. App.
2016
Read the full case

Background

  • StarStone (exclusive licensee) and E. Khashoggi Industries (guarantor) entered a Unit Purchase Agreement (UPA) with Manufacturers Equipment Co. (MECO) requiring StarStone to pay the balance of $110,000 “within three (3) days after commissioning of the Russian main and coating lines.”
  • MECO’s subsidiary built a Russian production line with a main line and a coating line for KGS; MECO alleges commissioning occurred April 6, 2010; StarStone admits coating-line commissioning but disputes main-line commissioning.
  • MECO sued StarStone and EKI for breach of contract after StarStone failed to pay; cross-motions for summary judgment followed.
  • MECO submitted in reply a previously unfiled affidavit and a signed “Deed of Equipment Line Commissioning” dated April 6, 2010, showing KGS and MECO acceptance; defendants moved to strike the reply as untimely and presenting new evidence.
  • The trial court granted summary judgment to MECO and denied the motion to strike; the appellate court reversed and remanded, finding a genuine dispute over main-line commissioning and that the trial court should have allowed defendants an opportunity to respond to the newly submitted Deed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether StarStone breached UPA paragraph 2(c) by failing to pay within 3 days after commissioning MECO: Both lines (main and coating) were commissioned (Deed dated April 6, 2010); payment due and unpaid StarStone: Coating commissioned but main line never commissioned; KGS never accepted main line so condition precedent unmet Reversed and remanded: genuine factual dispute exists about main-line commissioning; summary judgment premature unless defendant allowed to respond to the Deed and fails to show a triable issue
Whether the trial court erred by overruling the motion to strike MECO’s reply evidence MECO: Deed and affidavit support commissioning and were properly considered in ruling StarStone: Reply introduced new evidence/argument by ambush; trial court should have struck the reply or allowed a surreply Reversed: trial court abused discretion by not giving StarStone an opportunity to respond to critical new evidence; remand to permit surreply and re-evaluate summary judgment burden

Key Cases Cited

  • Anderson v. Liberty Lobby, 477 U.S. 242 (summary-judgment standard and genuine-issue inquiry)
  • GNFH, Inc. v. W. Am. Ins. Co., 172 Ohio App.3d 127 (2d Dist.) (de novo review of summary judgment)
  • Smith v. Five Rivers MetroParks, 134 Ohio App.3d 754 (2d Dist.) (summary-judgment standard; construing evidence for nonmoving party)
  • Napier v. Brown, 24 Ohio App.3d 12 (2d Dist.) (role of trial court is to determine existence of triable issues, not resolve credibility)
  • In re Fuel Adjustment Clauses for Columbus S. Power Co. & Ohio Power Co., 140 Ohio St.3d 352 (Ohio 2014) (party may not raise new arguments or evidence for first time in reply)
Read the full case

Case Details

Case Name: Mfrs. Equip. Co. v. StarStone L.L.C.
Court Name: Ohio Court of Appeals
Date Published: Jun 3, 2016
Citations: 2016 Ohio 3276; 26725
Docket Number: 26725
Court Abbreviation: Ohio Ct. App.
Log In