History
  • No items yet
midpage
Metropolitan Edison Co. v. Pennsylvania Public Utility Commission
22 A.3d 353
Pa. Commw. Ct.
2011
Read the full case

Background

  • Consolidated petitions challenge a 2010 Public Utility Commission order reclassifying line losses as generation costs and barring TSC Rider recovery.
  • MetEd and Penelec sought to recover PJM line losses via the TSC Riders; the Commission held line losses are generation-related and not recoverable through TSC Riders.
  • OSBA cross-petitioned, challenging the allowance of carrying charges on under-collected transmission costs from unwinding generation contracts.
  • ALJ recommended line losses be recoverable as transmission costs; the Commission rejected that view and adopted the line-loss, generation-related conclusion.
  • The OSBA argued the Commission failed to provide adequate analysis under Section 703(e); remand was sought for the unwinding-generation-contract carrying charges.
  • The court affirms the line-loss holding, but remands to address OSBA's Exception No. 2 regarding carrying charges on the unwinding of generation contracts.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Are line loss costs transmission costs under 2803? MetEd/Penelec: line losses are transmission costs; should be in TSC Riders. Commission: line losses are generation-related, not transmission costs under 2803. Line losses are generation-related; not recoverable as transmission costs.
Is the Commission's factual finding supported by substantial evidence on line losses being generation-related? Companies assert the record shows line losses are transmission costs; the Commission mischaracterized evidence. The Commission's findings are supported by substantial evidence and credible weight given to Customers' witnesses. Yes; findings supported by substantial evidence.
Does the Order comply with the Filed Rate Doctrine and FERC precedent regarding line losses? FERC decisions treat line losses as transmission-related; state rejection would violate the Filed Rate Doctrine. FERC precedent is unclear; no direct conflict; state may interpret costs differently. No inconsistency with FERC precedent or Filed Rate Doctrine.
Did the Commission adequately address OSBA's Exception No. 2 on carrying charges related to unwinding generation contracts under Section 703(e)? OSBA, supported by NFG, requires detailed analysis of carrying charges; failure warrants remand. Order and RD addressed arguments; remand permissible but not required for this issue. Remand required to expressly address OSBA's Exception No. 2 consistent with this opinion.

Key Cases Cited

  • Metropolitan Edison Co. v. Pennsylvania Public Utility Commission, 960 A.2d 189 (Pa. Cmwlth. 2008) (congestion costs may be treated as transmission costs; MetEd I)
  • Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953 (Sup. Ct. 1986) (Filed Rate Doctrine; preemption concerns)
  • Popowsky v. Pennsylvania Public Utility Commission, 550 Pa. 449 (1997) (judicial deference to agency findings; substantial evidence standard)
  • ARIPPA v. Pennsylvania Public Utility Commission, 792 A.2d 636 (Pa. Cmwlth. 2002) (rate cap protections; cost-shifting principles)
  • National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission, 677 A.2d 861 (Pa. Cmwlth. 1996) (remand for adequate analysis under Section 703(e))
Read the full case

Case Details

Case Name: Metropolitan Edison Co. v. Pennsylvania Public Utility Commission
Court Name: Commonwealth Court of Pennsylvania
Date Published: Jun 14, 2011
Citation: 22 A.3d 353
Docket Number: 532 C.D. 2010, 632 C.D. 2010
Court Abbreviation: Pa. Commw. Ct.