Metropolitan Edison, Aplt. v. City of Reading
162 A.3d 414
| Pa. | 2017Background
- Met-Ed supplies electricity and its underground conduit banks run within the City of Reading’s right‑of‑way; portions are encased in terra cotta or PVC conduit.
- City sewer crews excavated near North 5th Street in July 2009, exposing and displacing earth supporting Met‑Ed’s conduit; a section of conduit fell into the trench.
- Met‑Ed hired Homan Excavating to patch and stabilize the conduit; Homan warned the City that the excavation walls were unstable and needed backfilling/shoring.
- The City continued excavating without shoring and did not backfill; heavy rain over the weekend washed away supporting soil and the conduit bank collapsed, requiring extensive repairs costing $53,000.
- Met‑Ed sued the City for negligence invoking the Utility Service Facilities exception to governmental immunity (42 Pa.C.S. § 8542(b)(5)). Trial court entered judgment for Met‑Ed; the Commonwealth Court reversed, concluding the dangerous condition originated from the City’s negligent excavation (thus immunity applied).
- The Pennsylvania Supreme Court granted review and reversed the Commonwealth Court, holding the Utility Exception applies where a dangerous condition of the agency’s utility facilities within the right‑of‑way caused the injury and the agency had notice but failed to remediate.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether § 8542(b)(5) (Utility Exception) applies when a dangerous condition exists in a local agency’s utility right‑of‑way even if the agency’s own excavation created that condition | Met‑Ed: Exception applies if a dangerous condition of the agency’s utility facilities in the right‑of‑way caused a reasonably foreseeable risk, and the agency had notice but failed to remediate | City: Exception does not apply where the dangerous condition originated from the agency’s negligent excavation; that is negligent conduct immune under the Tort Claims Act | Court: Utility Exception focuses on whether injury was caused by a dangerous condition of agency facilities in the right‑of‑way and notice/failure to remediate — genesis of the dangerous condition (including agency’s prior negligent act) is irrelevant; exception applies here |
| Whether plaintiff must prove the agency both created the dangerous condition and then failed to remediate it to pierce immunity | Met‑Ed: Creation by the agency is irrelevant; only notice and failure to remediate matter | City: Plaintiff must show City was responsible for placement of the unstable fill or otherwise created the condition | Court: Rejected requirement of two separate negligent acts; only failure to remediate a dangerous condition of the agency’s facilities after notice is the negligent act that triggers § 8542(b)(5) |
Key Cases Cited
- Miller v. Pa. Dep't of Transp., 690 A.2d (Pa. Commw.) (interpreting “of the facilities … located within rights‑of‑way” to include the strip of land disturbed for repairs)
- DeTurk v. South Lebanon Township, 542 A.2d (Pa. Commw.) (discusses application of utility exception in excavation contexts)
- Metropolitan Edison Co. v. Reading Area Water Auth., 937 A.2d 1173 (Pa. Commw. 2007) (held dangerous condition in that case originated from employees’ conduct and did not qualify as a dangerous condition of water authority facilities)
- Gall by Gall v. Allegheny County Health Dep’t, 555 A.2d (Pa.) (held plaintiffs sufficiently alleged a dangerous condition of water facilities of which authority had notice, applying the utility exception)
