History
  • No items yet
midpage
Metcalf Construction Co. v. United States
102 Fed. Cl. 334
Fed. Cl.
2011
Read the full case

Background

  • Metcalf commenced performance on a Navy design-build housing contract on December 31, 2002, with 32 contract modifications extending completion from March 5, 2005 to October 17, 2006 and ultimately to March 2, 2007.
  • The 212-unit Kaneohe Bay project arose from an April 5, 2001 Navy RFP that was split into base and option components; Metcalf was awarded the base item contract on October 22, 2002 after prior protests and debriefings.
  • NTP was due by November 21, 2002, but a GAO bid protest delayed action; Navy instructed Metcalf to suspend actions pending protest disposition before award and performance.
  • The Navy modified the contract repeatedly, including an option to 212 units, with final contract price around $49.95 million; Metcalf contends costs exceeded $76 million while Navy-paid amounts total about $49.05 million.
  • Metcalf filed suit November 5, 2007 alleging bad-faith conduct and delay/impact damages; court addressed jurisdiction, standing, cardinal-change theories, differing-site-conditions, and various contract-claim theories, ultimately denying liability but granting extensions for certain delays.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Jurisdiction under the Tucker Act and CDA Metcalf alleged contract-based money damages against the United States. Navy argues CDA jurisdiction and proper contractual remedies exist under the Changes and Differing Site Conditions clauses. Court has Tucker Act jurisdiction and CDA jurisdiction over pleaded claims.
Whether Metcalf’s cardinal-change theory was tried with consent Cardinal change theory arises from the same facts as the global/differing-site-condition claim. No express or implied trial-consent to a new cardinal-change theory; amendment denied. Denied; cardinal-change theory not tried with consent; Second Amended Complaint denied.
Differing site conditions and related extension Expansive soils and chlordane issues evidenced a differing site condition requiring equitable adjustment. No valid differing-site-condition existed or, if one did, Navy acted promptly or compensated appropriately. Navy violated FAR 52.236-2(b) by delaying investigation; Metcalf entitled to a 306-day extension; no direct recovery of site-condition costs as damages.
Chlordane remediation obligations and related conduct Contract implied remediation was not required; Navy actions on chlordane imposed costs on Metcalf. Contract required testing/remediation under environmental requirements; Navy paid some costs; no breach. Navy did not breach; contractor reasonably obligated to manage disposal/remediation under contract; limited reimbursement occurred.
Interference with design revisions and approvals of substitutions Navy improperly rejected qualified substitutes and constrained Metcalf’s prerogatives as design-builder. Rejections were based on comparability/equivalency with predecessors and contract requirements. No breach; Navy could deny substitutions not deemed comparable; no bad-faith breach found.

Key Cases Cited

  • Int'l Tech. Corp. v. Winter, 523 F.3d 1341 (Fed. Cir. 2008) (four-element test for site conditions claims)
  • Kinetic Builders, Inc. v. Peters, 226 F.3d 130 (Fed. Cir. 2000) (substantial completion requires usable facility per contract terms)
  • Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (good-faith/fair-dealing breach requires targeted reappropriation of benefits)
  • Ace Constructors, Inc. v. United States, 499 F.3d 1357 (Fed. Cir. 2007) (cardinal-change concept and limits in contract disputes)
  • Scott Timber Co. v. United States, 333 F.3d 1358 (Fed. Cir. 2003) (new claims may be adjudicated if arising from same operative facts)
  • England v. The Swanson Grp., Inc., 353 F.3d 1379 (Fed. Cir. 2004) (claim defined as a written demand for money in a sum certain)
Read the full case

Case Details

Case Name: Metcalf Construction Co. v. United States
Court Name: United States Court of Federal Claims
Date Published: Nov 30, 2011
Citation: 102 Fed. Cl. 334
Docket Number: No. 07-777C
Court Abbreviation: Fed. Cl.