Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc
2:20-cv-00935
N.D. Ala.Mar 14, 2022Background
- Plaintiff Metal Roofing Solutions, Inc. (MRS), a sub-subcontractor, contracted with Composite Manufacturing & Installers, Inc. (CMI) to install and caulk ACM panels for a UAB public project; the sub-subcontract price was $64,452.
- MRS took field measurements; delivered panels did not fit, and MRS performed corrective/refabrication work. After its last day on the project (May 19, 2019), MRS submitted five work orders totaling $119,151.23 for additional labor/materials.
- MRS executed conditional releases in April and June 2019 covering payments received through certain dates; later it and CMI entered a consent judgment in favor of MRS for $195,880.31 (including $119,151.23 principal). Travelers, the payment-bond surety for MJ Harris (prime contractor), rejected MRS’s bond claims.
- MRS sued Travelers under Alabama Code § 39-1-1 (the “little Miller Act”); cross-motions for summary judgment were filed by MRS and Travelers.
- The district court denied both summary-judgment motions, finding genuine disputes of material fact about (1) whether the post-performance work orders fall within the agreed contract sum and (2) whether the April/June releases waived MRS’s bond claim.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| 1) Are the five additional work orders (totaling $119,151.23) part of the agreed sub‑subcontract amount recoverable under the payment bond? | MRS: The work orders relate to the project and are included in the consent judgment with CMI, evidencing CMI’s approval and bringing the amounts within the subcontract sum. | Travelers: The sub‑subcontract required written/approved work orders; MRS failed to timely submit/obtain approval and therefore assumed responsibility for unapproved work. | Denied summary judgment — genuine factual dispute whether CMI approved the orders (timing/manner unresolved) and whether they fall within the contract sum. |
| 2) Did MRS’s April and June 2019 releases waive its little Miller Act claim? | MRS: Releases reference only labor/materials "invoiced to" by certain dates, and the additional work orders were submitted later, so MRS did not waive claims for those amounts. | Travelers: The releases and the June release’s broader language release claims "with respect to all received payments," which Travelers reads to bar MRS’s outstanding claims. | Denied summary judgment — release language is ambiguous and susceptible to more than one reasonable meaning; factual development required. |
| 3) Can Travelers assert offset/recoupment for MRS’s alleged contractual failures (e.g., punch list) against the claimed amounts? | MRS: Provides work orders, testimony, and the consent judgment as proof of amounts owed; says it didn’t complete punch list because CMI withheld payment. | Travelers: MRS has not sufficiently proven amounts and they may be subject to recoupment for MRS’s failure to complete contractual obligations. | Denied summary judgment — disputes about scope of work, causation, and whether recoupment applies preclude resolution now. |
| 4) Does the consent judgment between MRS and CMI bind Travelers / conclusively establish CMI’s approval of the work orders? | MRS: The consent judgment reflects CMI’s agreement MRS is owed $119,151.23 and thus supports MRS’s bond claim. | Travelers: A consent judgment binds only consenting parties and cannot impose obligations on a nonparty (the surety); it does not automatically bind Travelers. | Court accepts that the consent judgment may evidence CMI’s ratification but does not bind Travelers; factual questions remain, so summary judgment is inappropriate. |
Key Cases Cited
- Trane Co. v. Whitehurst-Lassen Constr. Co., 881 F.2d 996 (11th Cir. 1989) (Alabama payment-bond statute is remedial and construed liberally to secure payment).
- Johnson Controls, Inc. v. Liberty Mut. Ins. Co., 160 So. 3d 249 (Ala. 2014) (statutory focus on intent to furnish for public project; statute read into payment bonds).
- Fed. Ins. Co. v. I. Kruger, Inc., 829 So. 2d 732 (Ala. 2002) (elements for bond recovery and authority on Miller Act analogues).
- A.G. Gaston Constr. Co. v. Hicks, 674 So. 2d 545 (Ala. Civ. App. 1995) (amount recoverable by subcontractor measured by agreed contract amount).
- Safeco Ins. Co. of Am. v. Graybar Elec. Co., 59 So. 3d 649 (Ala. 2010) (exceptions to bond recovery include waiver, novation, estoppel).
- Price v. H.L. Cable Constr. Co., 317 F.2d 312 (5th Cir. 1963) (contract sum as measure of recovery under bond).
- Local No. 93, Int’l Ass’n of Firefighters v. City of Cleveland, 478 U.S. 501 (1986) (consent decrees cannot bind nonconsenting third parties).
- Wayne J. Griffin Elec., Inc. v. Dunn Constr. Co., 622 So. 2d 314 (Ala. 1993) (court may construe release language at summary judgment; unambiguous releases enforced as written).
