History
  • No items yet
midpage
MEMC Pasadena, Inc. v. Riddle Power, LLC
2015 Tex. App. LEXIS 8143
| Tex. App. | 2015
Read the full case

Background

  • MEMC Pasadena operated a polysilicon plant and contracted CDI as construction manager for the P-23 expansion; CDI ran the bid process and issued the RFP and multiple addenda.
  • Triad bid on a T&M electrical contract; CDI sent Addendum 9 (a mutual waiver of consequential damages) to all bidders; Triad received Addendum 9 pre-deadline and did not object in its bid.
  • A scheduling decision led to energized ("hot") work on transformer T-45; Triad subcontracted the hot work to Riddle, a high-voltage specialist.
  • During cable pulling, a metal fish tape contacted an energized bus (a missing protective lower deflector plate would have blocked contact), causing an explosion and plant shutdown; no injuries occurred.
  • MEMC sued Triad (breach of contract and negligence) and Riddle (negligence). Jury found Triad, Riddle, and MEMC negligent (30%/30%/40%) and found Triad breached contract but that Addendum 9 applied (waiving consequential damages); judgment awarded MEMC $90,000 against Riddle and nothing against Triad.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Addendum 9 (mutual consequential-damages waiver) became part of MEMC–Triad contract MEMC: CDI lacked authority to bind MEMC to Addendum 9; no express agreement or sufficient implied assent Triad: CDI acted with actual/apparent authority in the bid process; Triad received Addendum 9 and did not except to it Sufficient evidence supported that CDI (with MEMC approval) sent Addendum 9, Triad accepted it by bidding without exception, and MEMC is estopped from denying it; jury finding affirmed
Whether MEMC’s online T&Cs governed as a matter of law MEMC: PO language incorporated MEMC’s online T&Cs; directed verdict should have been granted Triad: surrounding evidence created fact issue about which T&Cs governed (CDI T&Cs v. MEMC online T&Cs) Jury question proper; evidence supported jury’s negative answer that online T&Cs applied
Whether CDI had actual or apparent authority to issue Addendum 9 MEMC: no documentary proof MEMC approved Addendum 9; witnesses lacked recall; Triad’s reliance was based on interested witness Triad: CDI repeatedly acted as MEMC’s agent for bids; witnesses testified MEMC approved addenda; Triad reasonably relied Evidence supported actual/apparent authority; jury finding affirmed
Whether Triad is liable in tort for economic losses (negligence claim) despite contract MEMC: Triad was actively negligent (distracting Riddle), causing physical/property damage and economic loss Triad: economic loss rule bars tort recovery where injury is purely contractual/economic Economic loss rule applies—MEMC’s claims against Triad sound in contract; negligence recovery barred; take-nothing judgment for Triad affirmed
Whether MEMC (via CDI) was negligent and its comparative responsibility (40%) MEMC: insufficient evidence that MEMC/CDI proximately caused the accident; CDI was agent only for bidding/management, not construction design/installation Triad/Riddle: CDI/MEMC failed to install/monitor protective barrier, delegated but had construction/safety authority, and MEMC personnel interrupted Riddle’s work Evidence legally and factually sufficient that CDI/MEMC breached duties (missing deflector plate installation/monitoring and interruption of work) and contributed to the accident; 40% allocation supported
Damages: adequacy and measure of lost-profits award ($300,000 jury finding; $90,000 recovery) MEMC: expert showed ~77.2 metric tons lost production worth ~$23.7M; jury award inadequate and court failed to instruct market-value minus cost measure Defendants: challenged the volume, market price, internal-transfer practices, and net-profit calculation; evidence supported a wide range of amounts Jury’s $300,000 lost-profits finding (and resulting $90,000 against Riddle) falls within the conflicting evidence range; no charge error shown on measure of lost profits

Key Cases Cited

  • City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005) (standards for legal and factual sufficiency review)
  • Sw. Bell Tel. Co. v. DeLanney, 809 S.W.2d 493 (Tex. 1991) (economic loss rule bars tort recovery where only economic loss is the subject of contract)
  • Jim Walter Homes, Inc. v. Reed, 711 S.W.2d 617 (Tex. 1986) (negligence claims grounded in contractual duties sound in contract)
  • Crown Life Ins. Co. v. Casteel, 22 S.W.3d 378 (Tex. 2000) (improper commingling of liability theories in broad-form questions can be harmful error)
  • Lear Siegler, Inc. v. Perez, 819 S.W.2d 470 (Tex. 1991) (more than one proximate cause may exist and jury allocates responsibility)
  • Exxon Corp. v. Emerald Oil & Gas Co., 348 S.W.3d 194 (Tex. 2011) (standard for reviewing directed verdict)
  • Golden Eagle Archery, Inc. v. Jackson, 116 S.W.3d 757 (Tex. 2003) (factfinder has broad discretion in awarding damages)
Read the full case

Case Details

Case Name: MEMC Pasadena, Inc. v. Riddle Power, LLC
Court Name: Court of Appeals of Texas
Date Published: Aug 4, 2015
Citation: 2015 Tex. App. LEXIS 8143
Docket Number: NO. 14-13-00117-CV
Court Abbreviation: Tex. App.