History
  • No items yet
midpage
552 S.W.3d 143
Mo. Ct. App.
2018
Read the full case

Background

  • MPO (medical office LLC) built a building on land owned by DSII; Jess Davis was sole member of DSII and 40% member/manager of MPO. A Ground Lease (with an absolute purchase option for land at $650,000) and a Settlement Agreement (Dec. 27, 2013) governed disentanglement.
  • Settlement Agreement required removing Davis as a member; his 40% interest value would be 40% of MPO net asset value (building equity minus loan), determined by an appraisal selected through a lender chosen by MPO’s manager; various offsets/penalties applied if closing was delayed.
  • Valbridge appraisal (selected by First Citizens Bank) valued building such that net equity was negative; Davis disputed that valuation and sought a second appraisal (Integra), which produced a similar result. MPO sent an April 14, 2014 letter calculating payoffs and stating it would exercise the Ground Lease purchase option and close soon; parties agreed to a May 22, 2014 closing but Davis did not cooperate.
  • MPO sued Davis and DSII; jury trials and court-tried equity claims were split. Jury found for MPO on breach of the Settlement Agreement and implied covenant (awarding $150,000 each) and for DSII on MPO’s Ground Lease nonpayment claim ($54,000). The court (equity) found Davis/DSII first breached by failing to close, denied Appellants’ requested declaratory relief/fees, and ordered specific performance per MPO’s April 14, 2014 calculations, offset by the jury award — but included an incorrect double-counted offset.
  • Appellants appealed multiple points (jurisdiction, jury trial rights, sufficiency/weight of evidence on option exercise, remedies, double recovery). The appellate court affirmed the judgment with modifications to avoid double recovery and corrected clerical references.

Issues

Issue Plaintiff's Argument (MPO) Defendant's Argument (Davis/DSII) Held
1. Subject-matter jurisdiction to adjudicate whether Appellants breached Ground Lease MPO: Circuit court has plenary jurisdiction over civil matters; breach was before the court via pleadings/defenses and trial by consent Davis: MPO failed to plead breach of Ground Lease; court lacked jurisdiction to decide it Affirmed: Webb controls—trial court had subject-matter jurisdiction; issue was legal error, not lack of jurisdiction.
2. Jury-trial/due-process right to have jury decide breach of Ground Lease MPO: Breach was an equity issue reserved for the court; parties treated it as such Davis: Fact question of breach should have been submitted to jury; court deprived constitutional jury right Denied (not preserved): Davis failed to timely raise constitutional claim and did not request jury submission.
3. Whether MPO properly exercised purchase option under Ground Lease MPO: April 14 letter sufficiently manifested exercise; parties waived strict procedural requirements by conduct/consent Davis: MPO failed to give 90-days' certified-mail notice and didn’t strictly follow lease procedure Affirmed: Trial court reasonably found exercise adequate and Appellants waived strict compliance; finding not against the weight of the evidence.
4. Whether Appellants could obtain declaratory relief terminating Ground Lease / attorneys’ fees after failing to close MPO: Appellants’ own bad faith and first breach (failure to close) bars equitable relief; unclean hands doctrine applies Davis: MPO breached first by nonpayment; Appellants entitled to termination/fees Affirmed: Court properly denied equitable relief and fees based on Appellants’ prior breach and lack of good faith.
5. Award of both monetary damages and specific performance for breach of Settlement Agreement (double recovery) MPO: Money damages under Sec.1.H were proper and specific performance necessary because damages alone were inadequate to sever relationships Davis: Cannot obtain both remedies or get a double recovery; judgment double-counted offsets Partially granted: Both remedies allowed, but appellate court corrected judgment to remove $94,104 offsets already reflected in jury damages to avoid double recovery.
6. Jury instruction / special interrogatory on fair market value of building Davis: Jury should have determined FMV (Interrogatory 18) MPO: Value issues were addressed and Appellants later withdrew the interrogatory; appraisal process was as agreed Denied (not preserved): Appellants withdrew/interrogatory abandoned; no preserved error.
7. Submission of implied covenant claim to jury MPO: Evidence showed Appellants failed to cooperate/act in good faith to close Davis: No legal/sufficient evidence to submit implied covenant claim Affirmed: Sufficient evidence to submit; damages overlap with breach-of-contract award but were handled via offsets.

Key Cases Cited

  • Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976) (standard of review for court-tried matters)
  • J.C.W. ex rel. Webb v. Wyciskalla, 275 S.W.3d 249 (Mo. banc 2009) (Missouri recognizes only subject-matter and personal jurisdiction; pleading defects generally do not deprive subject-matter jurisdiction)
  • Pilla v. Estate of Pilla, 689 S.W.2d 727 (Mo. App. E.D. 1985) (parties may waive strict contractual procedural requirements by conduct or oral agreement)
  • Metropolitan St. Louis Sewer Dist. v. Zykan, 495 S.W.2d 643 (Mo. 1973) (equity courts may decree specific performance and also award damages)
  • Doe 1631 v. Quest Diagnostics, Inc., 395 S.W.3d 8 (Mo. banc 2013) (equitable relief is inappropriate where adequate remedy at law exists)
Read the full case

Case Details

Case Name: Med. Plaza One, LLC v. Davis
Court Name: Missouri Court of Appeals
Date Published: May 29, 2018
Citations: 552 S.W.3d 143; WD 80729
Docket Number: WD 80729
Court Abbreviation: Mo. Ct. App.
Log In
    Med. Plaza One, LLC v. Davis, 552 S.W.3d 143