History
  • No items yet
midpage
Meadow Valley Contractors, Inc. v. State Department of Transportation
2011 UT 35
Utah
2011
Read the full case

Background

  • MVC contracted with UDOT for I-215 paving; Southwest subcontracted paving work under MVC.
  • At a June 2003 pre-pave meeting, Squire told MVC/Southwest ribbon paving was not allowed where it caused >2-inch vertical grade separation.
  • Southwest proposed a 5:1 or flatter taper to mitigate grade separation; Squire rejected it, maintaining ribbon paving was not permitted.
  • MVC/Southwest did not provide written notice within 5 days as required by contract §1.7 and continued work under the alleged change.
  • Southwest used block paving due to ribbon-paving ban, increasing costs; UDOT imposed a $166,416 thickness penalty for overall five-inch pavement
  • The Board of Review recommended denial; trial court awarded MVC damages; UDOT appealed; MVC cross-appealed on thickness interpretation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did UDOT breach by banning ribbon paving? MVC argued contract allowed ribbon paving and the ban breached. UDOT argued contract allowed changes; Ribbon ban valid under §1.5/§1.7. UDOT did not breach; contract allowed changes.
Did MVC waive/diminish claims by failing to give written notice within 5 days? MVC did not timely notice, waiving claims. Notwithstanding, §1.7 requires notice; failure to notice waives claims. MVC waived claims due to failure to provide timely written notice.
Did UDOT orally modify the contract's notice provisions? MVC claimed oral direction satisfied notice. No written modification; no modification of notice provisions. UDOT did not orally modify the notice provisions.
Is MVC entitled to damages for thickness penalty given ambiguity in thickness provisions? MVC argued 3/8-inch deficiency applies per lift. UDOT argued 3/8-inch applies to total five inches. Contract ambiguous; record supports UDOT’s interpretation; thickness denial affirmed.
Can an assignee recover damages in the assignor’s breach under SME Industries framework? Southwest seeks damages via MVC’s claims. Assignee cannot recover damages suffered by assignor; issue not preserved. Not reached on plain error; majority notes assignment issue is complex and not essential to ruling.

Key Cases Cited

  • Thorn Construction Co. v. Utah Department of Transportation, 598 P.2d 365 (Utah 1979) (written notice not required when engineer orders extra work)
  • SME Industries, Inc. v. Thompson, Ventulett, Stainback & Associates, Inc., 28 P.3d 669 (Utah 2001) (assignee may recover only damages suffered by assignor)
  • Procon Corp. v. Utah Department of Transportation, 876 P.2d 892 (Utah Ct. App. 1994) (footnote discussion on waiver of notice provisions)
Read the full case

Case Details

Case Name: Meadow Valley Contractors, Inc. v. State Department of Transportation
Court Name: Utah Supreme Court
Date Published: Jul 12, 2011
Citation: 2011 UT 35
Docket Number: No. 20090025
Court Abbreviation: Utah