History
  • No items yet
midpage
McConnell v. Servinsky Engineering, PLLC
22 F. Supp. 3d 610
W.D. Va.
2014
Read the full case

Background

  • McConnell hired Servinsky Engineering, PLLC to design a post foundation for a farm building in Virginia; Servinsky, a Virginia-licensed engineer and SE principal, personally performed the design under a written contract.
  • The foundation and posts allegedly failed to accommodate local loads, leading to cracking concrete piers, loosened nuts, split posts, and fabric roof damage; four addenda attempted to fix deficiencies.
  • Count Two alleges Servinsky individually liable for breach of professional standard of care, breach of implied warranty, and breach of implied contract based on his seal and professional status.
  • Servinsky moves for judgment on the pleadings arguing economic loss rule and lack of privity bar the claims; also challenges implied warranty and implied contract to plead.
  • Virginia law governs tort and contract aspects in this diversity case; the court must apply Virginia choice-of-law rules and assess whether economic loss and privity foreclose recovery.
  • The court grants the motion, holding no privity and no independent tort duty, and finds no viable implied warranty or implied contract theories against Servinsky.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the economic loss rule bars the professional-negligence claim McConnell relies on a negligent design claim for economic loss. Servinsky argues contract law provides sole remedy; privity required. Economic loss rule bars negligence claim; no privity exists.
Whether Servinsky's professional seal creates an independent tort duty Seal and status may create independent duty beyond contract. No independent tort duty arises from professional seal under Virginia law. No independent duty; duties arise from contract.
Whether privity defeats the implied warranty claim Implied warranty arises independently of contract with SE; Texas/VA analogies not needed. Implied warranty requires privity with Servinsky; no privity here. Implied warranty claim failed due to lack of privity.
Whether the implied contract claim is plausibly alleged There is an implied contract based on conduct with SE; Servinsky’s involvement may create implied terms. No separate implied contract with Servinsky; written contract governs. No plausible implied contract claim; dismissal granted.

Key Cases Cited

  • Sensenbrenner v. Rust, Orling & Neale Architects, Inc., 236 Va. 419 (1988) (economic loss limited to contract remedies; no tort recovery for economic loss)
  • Blake Constr. Co., Inc. v. Alley, 353 S.E.2d 724 (Va. 1987) (privity required for economic damages in negligence actions)
  • Beard Plumbing & Heating, Inc. v. Thompson Plastics, Inc., 152 F.3d 313 (4th Cir. 1998) (Virginia privity and economic loss principles applied in negligence)
  • Gerald M. Moore & Son, Inc. v. Drewry, 251 Va. 277 (1996) (absence of privity defeats economic loss claims against individual engineer)
  • Oleyar v. Kerr, 217 Va. 88 (1976) (professional duty arises from contract; no independent tort duty)
  • Comptroller of Va. ex rel. Va. Military Inst. v. King, 217 Va. 751 (1977) (negligence by professional prejudiced by contract framework)
  • Nelson v. Commonwealth, 235 Va. 228 (1988) (absent contract, professional duty implicit but not independent tort duty)
Read the full case

Case Details

Case Name: McConnell v. Servinsky Engineering, PLLC
Court Name: District Court, W.D. Virginia
Date Published: May 20, 2014
Citation: 22 F. Supp. 3d 610
Docket Number: Case No. 2:13CV00048
Court Abbreviation: W.D. Va.