McCaulley v. C L Enters.
309 Neb. 141
| Neb. | 2021Background
- Homeowners Richard and Michelle McCaulley acted as their own general contractor for a residence built beginning in 2006 and moved in late Feb/early Mar 2008.
- They separately contracted with multiple specialty contractors (plumbing, roofing, masonry, hardwood floors, doors/windows, waterproofing, retaining wall, etc.).
- On Feb. 7, 2012 (about 4 years after occupancy), the McCaulleys sued 12 contractors alleging negligence and implied-breach-of-warranty for defective workmanship; no express repair warranties were pleaded.
- Seven contractors moved for summary judgment under Neb. Rev. Stat. § 25-223, asserting each claim accrued when that contractor substantially completed its work; the McCaulleys argued accrual waited until the entire home was substantially complete.
- The district court granted summary judgment for the seven contractors (finding each claim time barred) and denied the McCaulleys’ oral motion to file a fourth amended complaint to add an express warranty-to-repair claim.
- The Nebraska Supreme Court affirmed, holding accrual ran from each contractor’s substantial completion date and that denial of leave to amend was not an abuse of discretion.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| When does § 25-223’s 4-year limitations period begin for defects by specialty contractors? | Accrual did not begin until the entire home was substantially complete (late Feb/early Mar 2008). | Accrual began when each contractor substantially completed its separate contracted work. | Accrual ran from each contractor’s substantial completion of its own project; claims were time barred. |
| Whether district court abused discretion by denying leave to amend to add an express warranty-to-repair claim | Amendment was justified (citing language in an Adams concurrence) and should be allowed to preserve a potentially later-accruing claim. | The amendment was untimely, prejudicial, and futile given lengthy delay and that summary-judgment briefing was complete. | Denial affirmed: court did not abuse discretion because of undue delay and unfair prejudice to defendants. |
Key Cases Cited
- Fuelberth v. Heartland Heating & Air Conditioning, 307 Neb. 1002, 951 N.W.2d 758 (2020) (statute begins to run at substantial completion; divisible contracts may produce separate accruals).
- Adams v. Manchester Park, 291 Neb. 978, 871 N.W.2d 215 (2015) (limitations period runs from substantial completion of project; concurrence discussed later-accruing repair warranties).
- Murphy v. Spelts-Schultz Lumber Co., 240 Neb. 275, 481 N.W.2d 422 (1992) (defective-workmanship claims accrue at substantial completion, not at date of specific act).
- Witherspoon v. Sides Constr. Co., 219 Neb. 117, 362 N.W.2d 35 (1985) (same substantial-completion accrual rule applied against general contractor).
- InterCall, Inc. v. Egenera, Inc., 284 Neb. 801, 824 N.W.2d 12 (2012) (leave to amend pleadings should be freely given absent undue delay, bad faith, futility, or unfair prejudice).
