McCaulley v. C L Enters.
309 Neb. 141
| Neb. | 2021Background:
- Richard and Michelle McCaulley acted as their own general contractor and hired separate subcontractors for discrete work on their Omaha home (roofing, plumbing, masonry, flooring, doors/windows, waterproofing, retaining wall).
- The homeowners moved into the house in late February/early March 2008 and filed a construction-defect suit on February 7, 2012 alleging negligence and breach of warranty against multiple subcontractors.
- Each defendant moved for summary judgment under Neb. Rev. Stat. § 25-223 (four-year limitations), asserting the limitations period began when that subcontractor substantially completed its work.
- The district court granted summary judgment for seven subcontractors, concluding the 4-year period ran from each contractor’s substantial completion date; it also denied the homeowners’ oral request to file a fourth amended complaint adding a breach-of-express-warranty-to-repair claim.
- The Nebraska Supreme Court affirmed: (1) the statute of limitations began to run on each subcontractor’s substantial completion date given separate contracts and no general contractor; (2) denial of leave to amend was not an abuse of discretion due to undue delay and unfair prejudice.
Issues:
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| When does the § 25-223 four-year limitations period begin to run for construction-defect claims against subcontractors? | The period should run from substantial completion of the entire house (single project). | The period runs from substantial completion of each subcontractor’s individual project (separate contracts). | Runs from each contractor’s substantial completion where homeowners acted as their own GC and contracted separately. |
| Did the district court abuse its discretion by denying leave to amend to add a breach-of-express-warranty-to-repair claim? | Leave should be allowed (relying on language in Adams concurrence). | Amendment was unduly delayed, prejudicial, and possibly futile given pending summary-judgment evidence. | Denial affirmed: amendment would cause undue delay and unfair prejudice; no abuse of discretion shown. |
Key Cases Cited
- Fuelberth v. Heartland Heating & Air Conditioning, 307 Neb. 1002, 951 N.W.2d 758 (Neb. 2020) (discusses divisible contracts and that limitations run from substantial completion of each divisible project)
- Adams v. Manchester Park, 291 Neb. 978, 871 N.W.2d 215 (Neb. 2015) (substantial-completion rule for homebuilder/general-contractor claims; concurrence noted warranty-to-repair accrual nuances)
- Witherspoon v. Sides Constr. Co., 219 Neb. 117, 362 N.W.2d 35 (Neb. 1985) (limitations runs from substantial completion of home for defective-construction claims against general contractor)
- Murphy v. Spelts-Schultz Lumber Co., 240 Neb. 275, 481 N.W.2d 422 (Neb. 1992) (applies § 25-223 to defective construction claims against builders/contractors)
- InterCall, Inc. v. Egenera, Inc., 284 Neb. 801, 824 N.W.2d 12 (Neb. 2012) (leave to amend pleadings "freely given when justice so requires" and limits on denial such as undue delay or prejudice)
