MCBEE v. SHANAHAN HOME DESIGN
2021 OK 60
| Okla. | 2021Background
- Plaintiff Vickie McBee filed suit on November 19, 2019 alleging construction defects against Shanahan Home Design, LLC and Biggs Backhoe, Inc.; counsel delayed issuance of summonses.
- Oklahoma Supreme Court issued three joint emergency administrative orders (SCAD Nos. 2020-24, 2020-29, 2020-36) in response to Covid-19, announcing a suspension/tolling of court deadlines from March 16, 2020 through May 15, 2020.
- Clerk issued summonses May 18, 2020; McBee served Biggs on July 8, 2020 and Shanahan on July 16, 2020 (both by certified mail).
- Defendants moved to dismiss under 12 O.S.Supp.2017 § 2004(I) (service must be made within 180 days of filing), arguing service was untimely; the trial court granted dismissal.
- On appeal, the Oklahoma Supreme Court reviewed de novo whether its emergency orders tolled the 180-day service period and whether the Court had authority to issue those orders.
- The Supreme Court reversed: it held the emergency SCAD orders tolled the § 2004(I) period (excluding March 16–May 15, 2020), so McBee’s July service fell within the tolled-adjusted deadline and dismissal was erroneous.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Oklahoma Supreme Court had authority to suspend or toll court deadlines during the Covid-19 emergency | The Court has constitutional supervisory/administrative power and rulemaking authority to issue emergency orders that suspend deadlines | Emergency administrative orders cannot alter or suspend statutory time limits absent express authority | Court: Supreme Court has constitutional administrative authority and Rule 2 power to issue such temporary emergency orders |
| Whether SCAD Orders tolled the 180‑day service period in 12 O.S.Supp.2017 § 2004(I) as applied to McBee | The SCAD orders treated March 16–May 15, 2020 as a tolling period; exclude those days from the 180‑day computation, making McBee’s July service timely | The 180‑day period ran regardless of the orders; McBee failed to serve within 180 days and dismissal was proper | Court: SCAD orders tolled the period; McBee had 63 days remaining after March 15 and service by July 16/July 8 was timely; reversal and remand |
Key Cases Cited
- SCAD No. 2020-24, 462 P.3d 704 (first joint emergency order suspending deadlines) (announced temporary suspension)
- SCAD No. 2020-29, 462 P.3d 262 (continued suspension and courthouse closures)
- SCAD No. 2020-36, 462 P.3d 703 (clarified tolling March 16–May 15 and resumption on May 16)
- Petuskey v. Cannon, 742 P.2d 1117 (1987) (Supreme Court has unified administrative control over courts)
- McGee v. Kirby, 118 P.2d 199 (1941) (time prevented by paramount authority is excluded in limitation computations)
- Cornett v. Carr, 302 P.3d 769 (2013) (§ 2004(I) 180‑day service limit is an outer limit; service is timely if within 180 days)
- Thompson v. Anchor Glass Container Corp., 73 P.3d 836 (2003) (explaining tolling as temporary suspension of statutory time bars)
