History
  • No items yet
midpage
Maryland Public Service Commission v. Federal Energy Regulatory Commission
394 U.S. App. D.C. 187
D.C. Cir.
2011
Read the full case

Background

  • PJM Interconnection proposed the Reliability Pricing Model (RPM) in 2005 to replace the old pricing model to boost investment in capacity.
  • FERC adopted the RPM with modifications, finding the old model unjust and unreasonable and approving the RPM with conditions.
  • RPM includes three mitigation measures for market power: require all available capacity in RPM auctions, substitute a proxy bid when market power is found, and encourage new entrants via multi-year rate commitments.
  • RPM auctions set prices three years in advance to allow new entrants to develop capacity, with shorter lags allowed for near-term deliveries.
  • Petitioners (Maryland Public Service Commission and New Jersey Board of Public Utilities) challenge the RPM’s rates as not just and reasonable; the Commission found no evidence of market power and attributed price increases to transmission constraints and increased reliability, supported by multiple analytic reports; the court reviews under a highly deferential, arbitrary-and-capricious standard and ultimately denies the petition for review.
  • The decision upholds the Commission’s orders as just and reasonable, citing substantial evidence that RPM promoted reliability and long-term investment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether RPM’s rate design is just and reasonable Petitioners argued RPM allows market power to inflate prices FERC concluded RPM’s design is just and reasonable and mitigates market power RPM just and reasonable; upheld
Whether the Commission properly addressed potential market-power abuse Petitioners contend shorter lag and actual bids enable abuse Commission found no evidence of market power after reviewing independent reports Commission-supported finding of no market-power abuse
Whether the record supports deference to the Commission under arbitrary-and-capricious review Challenges to the Commission’s factual findings on market power FERC’s findings are supported by substantial evidence and expert analyses Court upheld under arbitrary-and-capacious standard

Key Cases Cited

  • FPL Energy Maine Hydro LLC v. FERC, 287 F.3d 1151 (D.C.Cir. 2002) (agency findings are conclusive if supported by substantial evidence)
  • Pub. Utils. Comm'n v. FERC, 254 F.3d 250 (D.C.Cir. 2001) (rate design questions reviewed deferentially)
  • Sithe/Independence Power Partners v. FERC, 165 F.3d 944 (D.C.Cir. 1999) (highly deferential review of rate design decisions)
  • Blumenthal v. FERC, 552 F.3d 875 (D.C.Cir. 2009) (precedent on what petitioners must show in challenges to rates)
  • Tenn. Gas Pipeline Co. v. FERC, 860 F.2d 446 (D.C.Cir. 1988) (establishes that once a rate is found unjust, the Commission fixes the just and reasonable rate)
Read the full case

Case Details

Case Name: Maryland Public Service Commission v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Feb 8, 2011
Citation: 394 U.S. App. D.C. 187
Docket Number: 09-1296
Court Abbreviation: D.C. Cir.